Contents

executive summary                                                             

1                      Introduction                                                                          

1.1                   Background                                                                           

1.2                   Baseline Monitoring for the Contract                   

1.3                   Structure of the Baseline Monitoring Report   

2                      aIR qUALITY                                                                               

2.1                   Monitoring Requirement                                                  

2.2                   Monitoring Locations                                                       

2.3                   Monitoring Equipment                                                       

2.4                   Monitoring Parameters, Frequency and Duration 

2.5                   Monitoring Methodology and Quality Assurance/ Quality Control (QA/QC)                                                                                                       

2.6                   24 Hour TSP Monitoring                                                     

2.7                   1 Hour TSP Monitoring                                                       

2.8                   Baseline Monitoring Results                                        

2.9                   Action and Limit Level                                                        

3                      nOISE                                                                                           

3.1                   Monitoring Requirement                                                  

3.2                   Monitoring Locations                                                       

3.3                   Monitoring Equipment                                                       

3.4                   Monitoring Parameters, Frequency and Duration 

3.5                   Monitoring Methodology                                               

3.6                   Maintenance and Calibration                                       

3.7                   Baseline Monitoring Results                                        

3.8                   Action and Limit Levels                                                     

4                      Water quality                                                                        

4.1                   Monitoring Locations                                                       

4.2                   Monitoring Parameters and Frequency                 

4.3                   Monitoring Methodology                                               

4.4                   QA/QC Requirements                                                           

4.5                   Baseline Monitoring Results                                        

4.6                   Action and Limit Levels                                                     

5                      Ecology                                                                                    

5.1                   Baseline Walk-over Survey                                           

5.2                   Baseline Dolphin Monitoring                                        

5.3                   Baseline Bored Pilling Monitoring                            

6                      Conclusion                                                                             


 

LIST OF TABLES

 

Table 1

Baseline Air Quality Monitoring Period

Table 2

Baseline Noise Monitoring Period

Table 3

Baseline Water Quality Monitoring Period

Table 4

Baseline Dolphin Monitoring Period

Table 2.1

Air Quality Monitoring Equipment

Table 2.2

Frequency and Parameters of Air Quality Monitoring

Table 2.3

Summary of Baseline 1-hour TSP Monitoring Results

Table 2.4

Summary of Baseline 24-hour TSP Monitoring Results

Table 2.5

Guidelines for Establishing Action and Limit Levels for Air Quality

Table 2.6

Action and Limit Levels for 1-hour TSP

Table 2.7

Action and Limit Levels for 24-hour TSP

Table 3.1

Frequency and Parameters of Noise Monitoring

Table 3.2

Summary of Daytime Noise Monitoring Results (Normal Weekdays)

Table 3.3

Summary of Evening-Time & Daytime (Holidays) Noise Monitoring Results

Table 3.4

Summary of Night-Time Noise Monitoring Results

Table 3.5

Action Limit Levels for Noise during Construction Period

Table 4.1

Marine Water Quality Monitoring Locations

Table 4.2

Water Quality Monitoring Parameters and Frequency

Table 4.3

Water Quality Monitoring Equipment

Table 4.4

Methods for Laboratory Analysis for Water Samples

Table 4.5

Action and Limit Levels for Water Quality

Table 4.6

Action and Limit Levels for Water Quality

Table 5.1

Types of Habitats observed in Walk-over Survey

Table 5.2

Date of Baseline Dolphin Monitoring

Table 5.3

Dolphin Encounter Rates (Sightings Per 100 km of Survey Effort) during the Baseline Monitoring Period (September ¡V November 2011)

Table 5.4

Action Level and Limit Level for Dolphin Impact Monitoring

Table 5.5

Derived Value of Action Level (AL) and Limit Level (LL)

Table 5.6

Implementation of Event-Action Plan

Table 5.7

Values of the two response variables of dolphin acoustic behaviour collected by calibrated hydrophone (mean clicks and whistles per minutes) by size of group, behavioural state and time of day during baseline period

Table 5.8

Action Level (AL) and Limit Level (LL) for all response variables by size of group, behavioural state and time of day

Table 5.9

Event and Action Plan on Dolphin Acoustic Behaviour

                                            

LIST OF FIGURES

 

Figure 1.1        Contract Layout and Location of Monitoring Stations

Figure 5.1        Updated Habitat Map after Walk Over Survey

Figure 5.2        Layout of Transect Lines of Dolphin Monitoring in Northwest and Northeast Lantau Areas

Figure 5.3        Location of Pak Mong Station in NE Lantau with alignment of TM-CLKL southern connection viaduct

Figure 5.4        Fix positions of vessels (green dots) and dolphins (purple triangle) from Pak Mong Theodolite Tracking Station in relation to TM-CLKL alignment and HKBCF/HKLR reclamation sites in Sep 9th ¡V Oct 14th 2013

Figure 5.5        Track lines of the only dolphin group that was tracked and analyzed for movement and behavioural patterns in the present study

Figure 5.6        Distribution of Chinese white dolphin sightings in Northeast Lantau during January 2002 ¡V December 2013

Figure 5.7        Distribution of Chinese white dolphin sightings during TM-CLKL acoustic surveys (Sep 26th ¡V Oct 25th 2013)

Figure 5.8        Location of the bored pile pier sites to be monitored for the underwater noise measurement study of TM-CLKL construction

Figure 5.9        Mean bandlevels for the 122 recordings containing dolphin vocalizations

Figure 5.10      Mean bandlevels for all 440 recordings as a function of time of day

Figure 5.11      Map showing the tentative location of EAR deployments, pier sites to be monitored as well as pre-defined route for dolphin acoustic behavioural study

Figure 5.12      The summed length of recordings in minutes made for each day of observational effort during the baseline acoustic monitoring in September ¡V October 2013

Figure 5.13      Mean number of whistles per minute and clicks per minute recorded as a function of dolphin behavioural state

Figure 5.14     Histogram of the percentage of EAR recordings with dolphin detections made at site C1 (Bridge Alignment Area) during 30 days of the deployment period

Figure 5.15     The number of dolphin encounters and the mean encounter duration for each day recorded on the EAR at site C1 (Bridge Alignment Area)

Figure 5.16      Histogram of the percentage of EAR recordings at site C2 (near Lung Kwu Chau), with dolphin detections made during 30 days of the deployment period

Figure 5.17      The number of dolphin encounters and the mean encounter duration for each day recorded on the EAR at site C2 (near Lung Kwu Chau)



LIST OF APPENDICES

 

Annex A1        Calibration Certificate for Air Quality Monitoring Equipment

Annex A2        1-hour TSP Baseline Monitoring Results

Annex A3        Graphical Presentation of Baseline 1-hour TSP Levels

Annex A4        24-hour TSP Baseline Monitoring Results

Annex A5        Graphical Presentation of Baseline 24-hour TSP Levels

Annex B1        Copies of Calibration Certificates for Noise Monitoring Equipment

Annex B2        Day-time 07:00-19:00 hrs Baseline Noise Monitoring Data

Annex B3        Evening-time 19:00-23:00 hrs and Holidays 07:00-19:00hrs Baseline Noise Monitoring Data

Annex B4        Night-time 23:00-07:00 hrs of the next day Baseline Noise Monitoring Data

Annex B5        Graphical Presentation of Baseline Noise Levels

Annex C1       Copies of Calibration Certificates for Water Quality Monitoring Equipment

Annex C2       Quality Control Report for Laboratory Analysis

Annex C3       Baseline Water Quality Monitoring Results

Annex C4       Graphical Presentation of Baseline Water Quality Monitoring Data

Annex D         Baseline Dolphin Monitoring Report Prepared by Chinese White Dolphin (CWD) Service Contract No. HY/11/02

Annex E          Baseline Air Quality, Noise and Water Quality Monitoring Schedule 

Annex F          Weather Conditions during Baseline Monitoring Period

Annex G         Baseline Monitoring Report for Land-based Dolphin Behavioural and Movement Monitoring

Annex H         Baseline Monitoring Report for Underwater Noise and Dolphin Acoustic Behavioural Monitoring

 

EXECUTIVE SUMMARY

Under Contract No. HY/2012/07, Gammon Construction Limited is commissioned by the Highways Department (HyD) to undertake the design and construction of the Southern Connection Viaduct Section of Tuen Mun ¡V Chek Lap Kok Link (TM-CLKL) (¡§the Contract¡¨).  ERM-Hong Kong, Limited (ERM) has been appointed as the Environmental Team (ET) for the Contract.

According to the requirements of the Environmental Monitoring and Audit Manual (EM&A Manual) which is prepared for the TM-CLKL Project (Register No.: AEIAR- 146/2009), baseline monitoring has been undertaken prior to commencement of the construction works of the Contract.  This Baseline Monitoring Report presents findings of the following baseline monitoring components:

Ÿ  Air Quality;

Ÿ  Noise;

Ÿ  Water Quality; and

Ÿ  Ecology (including baseline walk-over survey, baseline dolphin monitoring and baseline bored piling monitoring).

Before the commencement of the Contract, HyD employed environmental specialists under Agreement No. CE35/2011 (EP) and Contract No. HY/2011/02 to conduct baseline environmental monitoring of air quality, noise, water quality and ecology to facilitate early commencement of construction of Hong Kong Boundary Crossing Facility (HKBCF) reclamation works and TM-CLKL advance Southern Landfall reclamation works under Contract No. HY/2010/02.  The baseline environmental monitoring was undertaken between September and November 2011 in accordance with requirements in the EM&A Manuals for the Hong Kong Link Road (HKLR), HKBCF and TM-CLKL.  A Baseline Environmental Monitoring Report (Version C) for Hong Kong-Zhuhai-Macao Bridge Hong Kong Projects ¡V Investigation (hereafter referred to as ¡§BEMR¡¨) was prepared to fulfill the Environmental Permits¡¦ conditions for HKBCF (including TM-CLKL southern landfall) Project ([1]).

 

In the present baseline monitoring report, relevant baseline monitoring results for air quality, noise, water quality and ecology (baseline dolphin monitoring) presented in the BEMR have been adopted for this Contract.  In addition, baseline water quality monitoring, baseline bored piling monitoring and baseline walk-over survey have been undertaken in the period of August to October 2013 to collect additional baseline monitoring data for the Contract which were not covered by the 2011 baseline monitoring.

 

The baseline monitoring works undertaken for air quality, noise, water quality and ecology for the Contract are presented in Tables 1-4 below.

Air Quality

Table 1           Baseline Air Quality Monitoring Period

Monitoring Stations

Baseline Monitoring Period

ASR 9A ¡V Siu Ho Wan MTRC Depot

18/10/2011 ¡V 31/10/2011

ASR 9C ¡V Siu Ho Wan MTRC Depot

During the monitoring, there was no major dust generating activities undertaken in the vicinity of the two monitoring stations (Table 1).  Data collected were reviewed and analyzed to determine the Action and Limit Levels for air quality which will be used for the impact monitoring throughout the construction of the Contract.  Details on the monitoring methodology, locations and results are presented in Section 2.

 

Noise

 

Table 2            Baseline Noise Monitoring Period

 

Monitoring Station

Baseline Monitoring Period

NSR 1 ¡V Pak Mong Village

18/10/2011-1/11/2011

Monitoring data collected was reviewed and analyzed in accordance with requirements of the EM&A Manual.  Details on the methodology, locations and results of monitoring are presented in Section 3 of this report.  The baseline noise monitoring data was analyzed for the following periods:

¡P      Daytime:            0700-1900 hrs on normal weekdays

¡P      Evening-time:     1900-2300 hrs

¡P      Holiday-time:      0700-1900 hrs on holidays

¡P      Night-time:           2300-0700 hrs of next day

Water Quality

Table 3           Baseline Water Quality Monitoring Period   

Monitoring Stations

Parameters, unit

Baseline Monitoring Period (1)

IS(Mf)9, IS(Mf)16, IS8, SR4, CS(Mf)3, CS(Mf)5

Ÿ  Temperature(¢XC)

Ÿ  pH(pH unit)

Ÿ  Turbidity (NTU)

Ÿ  Water depth (m)

Ÿ  Salinity (ppt)

Ÿ  Dissolved Oxygen (DO) (mg/L and % of saturation)

Ÿ  Suspended solids (SS) (mg/L)

6/10/2011 ¡V 31/10/2011

SR4a (2)

29/8/2013 ¡V 24/9/2013

Notes:

(1)    3 days per week, at mid-flood and mid-ebb tides, for a period of 4 weeks prior to the commencement of the marine works)

(2)   Additional baseline water quality monitoring was undertaken at SR4a for this Contract as per recommendation of the Environmental Review for the Temporary Staging for Construction of the Southern Connection (ERM, 2013).

 

Details of the baseline water quality monitoring are presented in Section 4.  The collected data were used to establish the Action and Limit Levels for Dissolved Oxygen (DO), Turbidity and Suspended Solids (SS) for the impact monitoring throughout the construction of the Contract.

 

Ecology

 

Baseline walk-over survey was undertaken on 13 and 24 September 2013 to confirm the existing ecological conditions before commencement of the Contract¡¦s construction works with reference to the habitat maps presented in the EIA Report.  Findings of the baseline walk-over survey are presented in Section 5.1.

Table 4          Baseline Dolphin Monitoring Period

Date of Baseline Dolphin Monitoring

1

05/09/2011

2

07/09/2011

3

16/09/2011

4

23/09/2011

5

06/10/2011

6

10/10/2011

7

13/10/2011

8

17/10/2011

9

28/10/2011

10

01/11/2011

11

02/11/2011

12

05/11/2011

13

06/11/2011

14

07/11/2011

 

Baseline dolphin monitoring was undertaken from September to November 2011.  Details on the monitoring methodology, locations and findings are presented in Section 5.2.  Determination of Action and Limit Levels for dolphin monitoring is also presented under the same section.

 

Baseline bored piling monitoring, including land-based theodolite tracking, underwater noise monitoring and acoustic behavioural monitoring, were undertaken from September to October 2013.  Details on the monitoring methodology, locations and findings are presented in Section 5.3.  Determination of Action and Limit Levels as well as the Event Action Plan for the bored piling monitoring is also presented under the same section.


1                                             Introduction

1.1                                      Background

According to the findings of the Northwest New Territories (NWNT) Traffic and Infrastructure Review conducted by the Transport Department, Tuen Mun Road, Ting Kau Bridge, Lantau Link and North Lantau Highway would be operating beyond capacity after 2016.  This forecast has been based on the estimated increase in cross boundary traffic, developments in the Northwest New Territories (NWNT), and possible developments in North Lantau, including the Airport developments, the Lantau Logistics Park (LLP) and the Hong Kong ¡V Zhuhai ¡V Macao Bridge (HZMB).  In order to cope with the anticipated traffic demand, two new road sections between NWNT and North Lantau ¡V Tuen Mun ¡V Chek Lap Kok Link (TM-CLKL) and Tuen Mun Western Bypass (TMWB) are proposed.

An Environmental Impact Assessment (EIA) of TM-CLKL was prepared in accordance with the EIA Study Brief (No. ESB-175/2007) and the Technical Memorandum of the Environmental Impact Assessment Process (EIAO-TM).  The EIA Report was submitted under the Environmental Impact Assessment Ordinance (EIAO) in August 2009.  Subsequent to the approval of the EIA Report (EIAO Register Number AEIAR-145/2009), an Environmental Permit (EP-354/2009) for TM-CLKL was granted by the Director of Environmental Protection (DEP) on 4 November 2009, and EP variation (EP-354/2009A) was issued on 8 December 2010. 

Under Contract No. HY/2012/07, Gammon Construction Limited is commissioned by the Highways Department (HyD) to undertake the design and construction of the Southern Connection Viaduct Section of TM-CLKL (¡§the Contract¡¨), including the following:

¡P      A dual 2-lane main marine crossing (Structures E2, E5, E6, E7 and E8) across the sea between the southern landfall of TM-CLKL and NLH;

¡P      Five link or slip roads (Structures F1, F2, F3, F4 and F5) at the southern landfall of TM-CLKL connecting a dual 2-lane rural trunk road (main marine crossing) in (i) above with the HKBCF and the TM-CLKL Northern Connection Sub-sea Tunnel Section;

¡P      Four link roads (Structures E1, A1, A2, B1, B2, B3,C1, C2, C3, C4, D1, D2, D3 and D4) at North Lantau connecting the main marine crossing in (i) above with the NLH ;

¡P      Associated civil, structural, geotechnical, marine, environmental protection, landscaping, drainage, highway electrical and mechanical (E&M) works, street lightings, traffic aids and sign gantries, marine navigational aids, ship impact protection system, water mains and fire hydrants, lightning protection system, SHMS, as well as operation and maintenance provisions of viaducts, provisioning of facilities for installation of TCSS, provisioning of facilities for installation of telecommunication cables/equipment and reprovisioning works of affected existing facilities/utilities; and

¡P      Incidental works thereto the above and other associated works which are shown on the Drawings or specified in the Contract.

Layout of the Contract components is presented in Figure 1.1. 

ERM-Hong Kong, Limited (ERM) has been appointed as the Environmental Team (ET) for the Contract.

1.2                                      Baseline Monitoring for the Contract

The scope of the EM&A programme follows the demarcation of monitoring responsibilities set out in Environmental Project Office¡¦s letter dated 29.10.2013.  Under the defined scope and according to relevant requirements of the Environmental Monitoring and Audit Manual (EM&A Manual) which is prepared for the TM-CLKL Project (Register No.: AEIAR- 146/2009), baseline monitoring has been undertaken prior to commencement of the construction works of the Contract.  This Baseline Monitoring Report presents findings of the following baseline monitoring components:

Ÿ  Air Quality;

Ÿ  Noise;

Ÿ  Water Quality; and

Ÿ  Ecology (including baseline walk-over survey, baseline dolphin monitoring and baseline bored piling monitoring).

 

Before the commencement of the Contract, HyD employed environmental specialists under Agreement No. CE35/2011 (EP) and Contract No. HY/2011/02 to conduct baseline environmental monitoring of air quality, noise, water quality and ecology to facilitate early commencement of construction of Hong Kong Boundary Crossing Facility (HKBCF) reclamation works and TM-CLKL advance Southern Landfall reclamation works under Contract No. HY/2010/02.  The baseline environmental monitoring was undertaken between September and November 2011 in accordance with requirements in the EM&A Manuals for the Hong Kong Link Road (HKLR), HKBCF and TM-CLKL.  A Baseline Environmental Monitoring Report (Version C) for Hong Kong-Zhuhai-Macao Bridge Hong Kong Projects ¡V Investigation (hereafter referred to as ¡§BEMR¡¨) was prepared to fulfil the Environmental Permits¡¦ conditions for HKBCF (including TM-CLKL southern landfall) Project ([2]).

In the present baseline monitoring report, relevant baseline monitoring results for air quality, noise, water quality and ecology (baseline dolphin monitoring) presented in the BEMR have been adopted for this Contract.  In addition, baseline water quality monitoring, baseline bored piling monitoring and baseline walk-over survey have been undertaken in the period of August to October 2013 to collect additional baseline monitoring data for the Contract which were not covered by the 2011 baseline monitoring.  Based on findings from the 2011 and 2013 baseline monitoring, baseline levels for air quality, noise, water quality and ecology are set out in this report for the Contract in accordance with the EM&A Manual.  These baseline levels will be used as the basis for compliance check during the impact monitoring in the construction of the TM-CLKL southern viaduct.  Locations, schedule, methodology and results for the baseline monitoring are also presented in this report.

1.3                                      Structure of the Baseline Monitoring Report

Following this introductory section, the remainder of the Report is structured as follows:

Section 2    Air Quality ¡V presents the methodology and findings of the baseline air quality monitoring.

Section 3    Noise ¡V presents the methodology and findings of the baseline noise monitoring.

Section 4    Water Quality ¡V presents the methodology and findings of the baseline water quality monitoring.

Section 5    Ecology ¡V presents the methodology and findings of the baseline walk-over survey, baseline dolphin monitoring as well as baseline bored piling monitoring programme.

Section 6    Conclusion

2                                             aIR qUALITY

2.1                                      Monitoring Requirement

According to the EM&A Manual of the TM-CLKL Project, baseline air quality monitoring should be carried out for a period of not less than 14 days to collect baseline data on 1-hour and 24-hour Total Suspended Particulates (TSP) levels at all monitoring locations.  Monitoring of 1-hour TSP should be carried out at least three times per day while that of 24-hour TSP should be conducted daily for 14 consecutive days.  Further details of the baseline air quality monitoring are presented in the following sections.

2.2                                      Monitoring Locations

Baseline air quality monitoring was conducted at two (2) monitoring stations (ie ASR9A and ASR9C ¡V Siu Ho Wan MTRC Depot) under this Contract.  Locations of the two monitoring stations, ASR9A and ASR9C, are shown in Figure 1.1. 

2.3                                      Monitoring Equipment

High Volume Samplers (HVS) were used to carry out the 24-hour TSP monitoring.  Direct reading dust meter was used to measure 1-hour average TSP levels.  The 1-hour TSP level was determined periodically by HVS to check the validity and accuracy of the results measured by the direct reading method.

 

Wind data monitoring equipment was set at Rooftop of Village Office at San Tau for logging wind speed and wind direction such that the wind sensors are clear of obstructions or turbulence caused by building.  The wind data monitoring equipment is recalibrated at least once every six months.  

 

Table 2.1 summarizes the equipment used in the baseline air quality monitoring programme.  Copies of the calibration certificates for the equipment are presented in Annex A1.

Table 2.1        Air Quality Monitoring Equipment

Equipment

Model and Make

Quantity

HVS Sampler

 

GMWS 2310 c/w of TSP sampling inlet

9

Calibrator

 

G25A

1

1-hour TSP Dust Meter

 

Laser Dust Monitor ¡V Model LD3/3B

7

Wind Anemometer

Davis Weather Monitor II, Model no. 7440

1

2.4                                      Monitoring Parameters, Frequency and Duration

Table 2.2 summarizes the monitoring parameters, monitoring period and frequency of baseline air quality monitoring.

Table 2.2        Frequency and Parameters of Air Quality Monitoring

Monitoring Station

Location for Measurement

Parameter

Period

Frequency

ASR 9A

Near Security Office of Siu Ho Wan MTRC Depot

 

1-hour TSP


24-hour TSP

0700-1900 for 1-hour TSP


24 hours for 24-hour TSP

 

3 times/ day for 1-hour TSP


Daily for 24-hour TSP

ASR 9C

Near Staff Canteen of Siu Ho Wan MTRC Depot

2.5                                      Monitoring Methodology and Quality Assurance/ Quality Control (QA/QC)

Weather data was recorded during the baseline period and is shown in Annex F.  The air temperature, precipitation and the relative humidity data were obtained from Hong Kong Observatory while wind speed and direction were recorded by the installed Wind Anemometer.  The general weather conditions (i.e. sunny, cloudy or rainy) were recorded by the field staff on the monitoring days.

2.6                                      24 Hour TSP Monitoring

Instrumentation

High volume Samplers (HVS) completed with appropriate sampling inlets was employed for air quality monitoring.  Each sampler was composed of a motor, a filter holder, a flow controller and a sampling inlet and its performance specification complies with that required by USEPA Standard Title 40, Code of Federation Regulations Chapter 1 (Part 50).

HVS Installation

The following guidelines were adopted during the installation of HVS:

    Sufficient support was provided to secure the samplers against gusty wind;

    No two samplers were placed less than 2 m apart;

    The distance between the sampler and an obstacle, such as buildings, was at least twice the height that the obstacle protrudes above the sampler;

    A minimum of 2 m of separation from walls, parapets and penthouses was required for rooftop samples;

    A minimum of 2 m separation from any supporting structure, measured horizontally, was required;

    No furnaces or incineration flues were nearby;

    Airflow around the sampler was unrestricted;

    The samplers were more than 20 meters from the drip line; and

    Any wire fence and gate used to protect the sampler should not cause any obstruction during monitoring.

Filter Preparation

Fiberglass filters were used.  These filters have a collection efficiency of larger than 99% for particles of 0.3µm in diameter.  A HOKLAS accredited laboratory, Wellab Ltd., was responsible for the preparation of 24-hr conditioned and pre-weighed filter papers for the monitoring.

All filters were equilibrated in the conditioning environment for 24 hours before weighing.  The conditioning environment temperature was around 25 ¢XC and not varied by more than ¡Ó3 ¢XC; the relative humidity (RH) was <50% and not varied by more than ¡Ó5%.  

Operating/ Analytical Procedures

Operating/analytical procedures for the air quality monitoring were highlighted as follows:

Ÿ   Prior to the commencement of the dust sampling, the flow rate of the HVS was properly set (between 1.1 m3/min. and 1.4 m3/min.) in accordance with the manufacturer's instruction to within the range recommended in USEPA Standard Title 40, CFR Part 50.

Ÿ   The power supply was checked to ensure the sampler worked properly.

Ÿ   On sampling, the sampler was operated for 5 minutes to establish thermal equilibrium before placing any filter media at the designated air quality monitoring station.

Ÿ   The filter holding frame was then removed by loosening the four nuts and carefully a weighted and conditioned filter was centered with the stamped number upwards, on a supporting screen.

Ÿ   The filter was aligned on the screen so that the gasket formed an airtight seal on the outer edges of the filter.  Then the filter holding frame was tightened to the filter holder with swing bolts.  The applied pressure should be sufficient to avoid air leakage at the edges.

Ÿ   The shelter lid was closed and secured with the aluminum strip.

Ÿ   The timer was then programmed.  Information was recorded on the record sheet, which included the starting time, the weather condition and the filter number (the initial weight of the filter paper can be found out by using the filter number).

Ÿ   After sampling, the filter was removed and sent to the laboratory for weighing.  The elapsed time was also recorded.

Ÿ   Before weighing, all filters were equilibrated in a conditioning environment for 24 hours. The conditioning environment temperature should be between 25¢XC and 30¢XC and not vary by more than ¡Ó3¢XC; the RH should be < 50% and not vary by more than ¡Ó5%.  Weighing results were used for further analysis of TSP concentrations collected by each filter.

Maintenance and Calibration

The following maintenance/calibration was required for the HVS:

Ÿ   The high volume motors and their accessories were properly maintained. Appropriate maintenance such as routine motor brushes replacement and electrical wiring checking were made to ensure that the equipment and necessary power supply were in good working condition.

Ÿ   All HVS were calibrated (five point calibration) using Calibration Kit prior to the commencement of the baseline monitoring and thereafter at bi-monthly intervals.

2.7                                      1 Hour TSP Monitoring

Measuring Procedures

The 1-hour TSP levels were measured by the dust meter in accordance with procedures specified in the Manufacturer¡¦s Instruction Manual which are described as follows:

Ÿ   The 1-hour dust meter was placed at least 1.3 m above ground.

Ÿ   Set POWER to ¡§ON¡¨ and make sure that the battery level was not flash or in low level.

Ÿ   Allow the instrument to stand for about three (3) minutes with the cap of the air sampling inlet released.

Ÿ   Pushed the knob at MEASURE position.

Ÿ   Set time/mode setting to [BG] by pushing the time setting switch.  Then, started the background measurement by pushing the start/stop switch once.  It took approximately six (6) seconds to complete the background measurement.

Ÿ   Pushed the time setting switch to change the time setting display to [MANUAL] at the bottom left of the liquid crystal display.  Finally, pushed the start/stop switch to stop the measuring after 1 hour sampling.

Ÿ   Information such as sampling date, time, count value and site condition were recorded during the monitoring period.

Maintenance and Calibration

For the 1-hour dust meter, it should be checked and calibrated by HVS to determine the validity and accuracy of the results measured by direct reading method at 2-month intervals throughout the air quality monitoring period.

2.8                                      Baseline Monitoring Results

Under this Contract, baseline air quality monitoring was conducted at two (2) monitoring stations, namely ASR 9A and ASR 9C, at the Siu Ho Wan MTRC Depot during the period of 18 October and 2 November 2011.  The detailed monitoring schedule is presented in Annex E.

The monitoring data of ASR 9A and ASR 9C are summarized in Tables 2.3 and 2.4.  All monitoring data of 1- hour and 24-hour TSP are presented in Annexes A2 and A4, respectively.  Graphical presentations of the 1-hour TSP and 24-hour TSP results are shown in Annex A3 and A5, respectively.  Detailed weather conditions during the baseline monitoring period are presented in Annex F.

Table 2.3        Summary of Baseline 1-hour TSP Monitoring Results

Monitoring Station

Average TSP Concentration (µg/m3)
(Range)

ASR 9A ¡V Siu Ho Wan MTRC Depot

222.3
(71.2-463.6)

 

ASR 9C ¡V Siu Ho Wan MTRC Depot

219.9
(70.2-461.8)

Table 2.4        Summary of Baseline 24-hour TSP Monitoring Results

Monitoring Station

Average TSP Concentration (µg/m3)
(Range)

ASR 9A ¡V Siu Ho Wan MTRC Depot

74.1
(38.6-128.1)

 

ASR 9C ¡V Siu Ho Wan MTRC Depot

74.5
(45.1-113.4)

The weather was generally sunny and fine during the baseline monitoring period.  Road traffic dust is identified as the influencing factors which may affect the results of baseline monitoring.

2.9                                      Action and Limit Level

Guidelines for establishing the Action and Limit Levels for air quality monitoring during the construction of the Contract are presented in Table 2.5.

Table 2.5        Guidelines for Establishing Action and Limit Levels for Air Quality

Parameters

Action Level

Limit Level

1-hour TSP Level in µg/m3

For baseline level 384 µg/m3,
Action level = (Baseline level*1.3 + Limit level)/2
For baseline level > 384
µg/m3,
Action level = Limit level

 

500

24-hour TSP Level in µg/m3

For baseline level 200 µg/m3,
Action level = (Baseline level*1.3 + Limit level)/2
For baseline level > 200
µg/m3,
Action level = Limit level

260

Following the above guidelines, the Action and Limit Levels for air quality impact monitoring are determined and presented in Tables 2.6 and 2.7.

Table 2.6        Action and Limit Levels for 1-hour TSP

Location

Action Level, µg/m3

Limit Level, µg/m3

ASR 9A

394

500

ASR 9C

393

 

Table 2.7        Action and Limit Levels for 24-hour TSP

Location

Action Level, µg/m3

Limit Level, µg/m3

ASR 9A

178

260

ASR 9C

Should non-compliance with the air quality criteria occur, the ET, the IEC and the SOR and the Contractor shall undertake their specified actions in accordance with the Action Plan shown in Table 3.2.

 


Table 2.8        Event/ Action Plan for Air Quality

 

 

ACTION

EVENT

ET (1)

IEC (1)

SOR(1)

Contractor

Action Level

 

 

 

 

1. Exceedance for one sample

1.  Identify the source.

2.  Inform the IEC and the SOR.

3.  Repeat measurement to confirm finding.

4.  Increase monitoring frequency to daily.

1.  Check monitoring data submitted by the ET.

2.  Check Contractor¡¦s working method.

1.  Notify Contractor.

1. Rectify any unacceptable practice

2.  Amend working methods if appropriate

2. Exceedance for two or more consecutive samples

1. Identify the source.

2. Inform the IEC and the SOR.

3. Repeat measurements to confirm findings.

4. Increase monitoring frequency to daily.

5. Discuss with the IEC and the Contractor on remedial actions required.

6. If exceedance continues, arrange meeting with the IEC and the SOR.

7. If exceedance stops, cease additional monitoring.

1.  Check monitoring data submitted by the ET.

2.  Check the Contractor¡¦s working method.

3.  Discuss with the ET and the Contractor on possible remedial measures.

4.  Advise the SOR on the effectiveness of the proposed remedial measures.

5.  Supervisor implementation of remedial measures.

1.  Confirm receipt of notification of failure in writing.

2.  Notify the Contractor.

3.  Ensure remedial measures properly implemented.

1.  Submit proposals for remedial actions to IEC within 3 working days of notification

2.  Implement the agreed proposals

3.  Amend proposal if appropriate

 


 

3                                             nOISE

3.1                                      Monitoring Requirement

According to the EM&A Manual of TM-CLKL, baseline noise monitoring should be carried out for a period of fourteen (14) days at all designated monitoring locations.  The noise levels should be measured in terms of A-weighted equivalent continuous sound pressure level (Leq).  Details of the baseline noise monitoring are presented in the following sections.

3.2                                      Monitoring Locations

Baseline noise monitoring was conducted at one (1) monitoring station, namely NSR 1 at Pak Mong Village, under the Contract (Figure 1.1). 

3.3                                      Monitoring Equipment

Integrating Sound Level Meter was used for noise monitoring.  The meter is a Type 1 sound level meter capable of giving a continuous readout of the noise level readings including equivalent continuous sound pressure level (Leq) and percentile sound pressure level (Lx).  The meter used also complied with International Electrotechnical Commission Publications 651:1979 (Type 1) and 804:1985 (Type 1) specifications.  The noise monitoring equipment being used and copies of the calibration certificates for the sound level meter and calibrator are presented in Annex B1.

3.4                                      Monitoring Parameters, Frequency and Duration

In accordance with the EM&A Manual, baseline noise for the A-weighted levels Leq, L10 and L90 was recorded.  Data obtained from the baseline noise monitoring were processed and presented for the following periods:

 

¡P            Daytime: 0700-1900 hrs on normal weekdays

¡P            Evening time: 1900-2300 hrs

¡P            Holiday time: 0700-1900 hrs on holidays

¡P            Night time: 2300-0700 hrs of next day

 

The frequency and parameters of noise measurement are presented in Table 3.1.

 

Table 3.1        Frequency and Parameters of Noise Monitoring

Monitoring Station

Location for Measurement

Time Period

Duration, min

Parameter

NSR 1

Pak Mong Village (Roof Top of Pak Mong Watch Tower)

Daytime on normal weekdays (0700-1900 hrs)


Evening time on all days (1900-2300 hrs) and daytime during holidays (including Sundays) (0700-1900 hrs)

 

Night time on all days (2300-0700 hrs)

30 min


5min

Leq, L10 & L90

3.5                                      Monitoring Methodology

Façade measurement was taken at the monitoring station NSR1.  Weather data was recorded during the baseline period and is presented in Annex F.  The air temperature, precipitation and the relative humidity data were obtained from Hong Kong Observatory where the wind speed and direction were recorded by the installed Wind Anemometer.  The general weather conditions (i.e. sunny, cloudy or rainy) were recorded by the field staff on the monitoring days.

The monitoring procedures are as follows:

Ÿ   The microphone head of the head level meter was normally positioned 1 m exterior of the noise sensitive façade and lowered sufficiently so that the building¡¦s external wall acts as a reflecting surface.

Ÿ   For free field measurement, the meter was positioned away from any nearby reflective surfaces.  All records for free field noise levels would be adjusted with a correction of +3 dB(A). 

Ÿ   The battery condition was checked to ensure good functioning of the meter.

Ÿ   Parameters such as frequency weighting, time weighting and measurement time were set as follows:

-   frequency weighting:    A

-   time weighting:              Fast

-   measurement time:       5 minutes (Leq (30-min) would be determined for daytime noise by calculating the logarithmic average of six Leq (5min) data.)

Ÿ   Prior to and after noise measurement, the meter was calibrated using the calibrator for 94.0 dB at 1,000 Hz.  If the difference in the calibration level before and after measurement was more than 1.0 dB, the measurement was considered invalid and repeat of noise measurement was required after re-calibration or repair of the equipment.

Ÿ   Noise monitoring was carried out continuously for 24 hours during the 14 days baseline monitoring period.  Monitoring data were recorded and stored automatically within the sound level meter system.  At the end of the monitoring period, noise levels in term of Leq, L90 and L10 were recorded.  In addition, site conditions and noise sources were recorded when the equipment were checked and inspected every two days.

Ÿ   All the monitoring data stored in the sound level meter system were downloaded through the computer software, and all these data were checked and reviewed on computer.

3.6                                      Maintenance and Calibration

Maintenance and calibration procedures were follows:

Ÿ   The microphone head of the sound level meter and calibrator were cleaned with a soft cloth at quarterly intervals;

Ÿ   The sound level meter and calibrator were checked and calibrated at yearly intervals; and

Ÿ   Immediately prior to and following each noise measurement, the accuracy of the sound level meter should be checked using an acoustic calibrator generating known sound pressure level at known frequency.  Measurements may be accepted as valid only if the calibration levels from before and after the noise measurement agree to within 1.0 dB.

3.7                                      Baseline Monitoring Results

Baseline noise monitoring was conducted at the noise monitoring station NSR1 in the period of 18 October and 1 November 2011 for this Contract.  The monitoring schedule is shown in Annex E.

The baseline noise monitoring results are summarized in Tables 3.2 to 3.4.  All baseline noise monitoring results are presented in Annexes B2-B4.  Graphical presentations of the data are provided in Annex B5.  Weather conditions recorded during the baseline monitoring period are shown in Annex F.

Table 3.2        Summary of Daytime Noise Monitoring Results (Normal Weekdays)

Daytime

0700-1900 hrs on

normal weekdays

Range of Noise Level, dB(A)

Leq (30 min)

L10 (5 min)

L90 (5 min)

Mean

Max

Min

Mean

Max

Min

Mean

Max

Min

NSR 1

56.2

65.9

48.4

58.4

75.4

42.7

46.5

59.9

38.8

 

Table 3.3        Summary of Evening-Time & Daytime (Holidays) Noise Monitoring Results

Evening-time

1900-2300 hrs on all days & Daytime 0700-1900 hrs on holidays

Range of Noise Level, dB(A)

Leq (30 min)

L10 (5 min)

L90 (5 min)

Mean

Max

Min

Mean

Max

Min

Mean

Max

Min

NSR 1

54.7

68.0

41.4

58.1

72.1

42.7

45.5

59.6

39.1

Table 3.4        Summary of Night-Time Noise Monitoring Results

Night-time 2300-0700 hrs of the next day

Range of Noise Level, dB(A)

Leq (30 min)

L10 (5 min)

L90 (5 min)

Mean

Max

Min

Mean

Max

Min

Mean

Max

Min

NSR 1

50.1

69.1

37.0

53.0

73.6

38.4

42.2

52.0

35.2

The weather was generally sunny and fine during the baseline monitoring periods.  Insect and bird calling was noted as the influencing factors which may affect the baseline monitoring results.  

3.8                                      Action and Limit Levels

The Action and Limit Levels were established in accordance with the EM&A Manual.  The baseline noise level should be referenced during the compliance check during the impact noise monitoring period.  Table 3.5 presents the Action and Limit Levels for construction noise of the Contract.  Should non-compliance of the criteria occur, the ET, the IEC, the SOR and the Contractor shall undertake their specified actions in accordance with the Action Plan shown in Table 3.6.  

 

Table 3.5        Action Limit Levels for Noise during Construction Period

Time Period

Action Level

Limit Level

0700-1900 hrs on normal weekdays

When one documented complaint is received

75* dB(A)


Table 3.6        Event/ Action Plan for Construction Noise

 

 

ACTION

EVENT

ET

IEC

SOR

Contractor

Action Level

1.   Notify the IEC and the Contractor.

2.   Carry out investigation.

3.   Report the results of investigation to the IEC and the Contractor.

4.   Discuss with the Contractor and formulate remedial measures.

5.   Increase monitoring frequency to check mitigation effectiveness.

1. Review the analysed  results submitted by the ET.

2. Review the proposed remedial measures by the Contractor and advise the SOR accordingly.

3. Supervise the implementation of remedial measures.

1. Confirm receipt of notification of failure in writing.

2. Notify the Contractor.

3. Require the Contractor to propose remedial measures for the analysed noise problem.

4. Ensure remedial measures are properly implemented.

1. Submit noise mitigation proposals to IEC

2. Implement noise mitigation proposals

Limit Level

1. Notify the IEC, the SOR, the DEP and the Contractor.

2. Identify the source.

3.  Repeat measurement to confirm findings.

4. Increase monitoring frequency.

5. Carry out analysis of Contractor¡¦s working procedures to determine possible mitigation to be implemented.

6.  Inform the IEC, the SOR and the DEP the causes & actions taken for the exceedances.

7. Assess effectiveness of the Contractor¡¦s remedial actions and keep the IEC, the DEP and the SOR informed of the results.

8. If exceedance stops, cease additional monitoring.

1.  Discuss amongst the SOR, the ET and the Contractor on the potential remedial actions.

2. Review the Contractor¡¦s remedial actions whenever necessary to assure their effectiveness and advise the SOR accordingly.

3. Supervise the implementation of remedial measures.

1. Confirm receipt of notification of failure in writing.

2. Notify the Contractor.

3. Require the Contractor to propose remedial measures for the analysed noise problem.

4. Ensure remedial measures are properly implemented.

5. If exceedance continues, consider what activity of the work is responsible and instruct the Contractor to stop that activity of work until the exceedance is abated.

1. Take immediate action to avoid further exceedance

2. Submit proposals for remedial actions to IEC within 3 working days of notification

3. Implement the agreed proposals

4. Resubmit proposals if problem still not under control

5. Stop the relevant activity of works as determined by the SOR until the exceedance is abated.


4                                             Water quality

According to the EM&A Manual of TM-CLKL, baseline water quality monitoring should be carried out three (3) times per week for a period of four (4) weeks at all the monitoring locations prior to the commencement of marine works.  The measurement should be taken at all designated monitoring stations, including control stations, at mid flood (within ¡Ó1.75 hour of the predicated time) and mid-ebb (within ¡Ó1.75 hour of the predicated time) tides.  Further details of the baseline water quality monitoring under this Contract are presented in the following sections. 

4.1                                      Monitoring Locations

Baseline water quality monitoring was conducted at seven (7) monitoring stations under the Contract.  Coordinates of the monitoring stations are summarized in Table 4.1.  Locations of the monitoring stations are shown in Figure 1.1.  

Table 4.1        Marine Water Quality Monitoring Locations

Monitoring Stations

Coordinates

Easting

Northing

IS(Mf)9

813273

818850

IS(Mf)16

814328

819497

IS8

814251

818412

SR4

814760

817867

SR4a

815247

818067

CS(Mf)3

809989

821117

CS(Mf)5

817990

821129

4.2                                      Monitoring Parameters and Frequency

Table 4.2 summarizes the monitoring parameters, monitoring period and frequencies of the water quality monitoring.

 

Table 4.2        Water Quality Monitoring Parameters and Frequency

Monitoring Stations

Parameters, unit

Depth

Frequency

IS(Mf)9

IS(Mf)16

IS8

SR4

SR4a*

CS(Mf)3

CS(Mf)5

Ÿ Temperature(¢XC)

Ÿ pH(pH unit)

Ÿ Turbidity (NTU)

Ÿ Water depth (m)

Ÿ Salinity (ppt)

Ÿ DO (mg/L and % of

saturation)

Ÿ SS (mg/L)

3 water depths: 1m

below sea surface,

mid-depth and 1m

above sea bed.

Baseline monitoring: 3 days

per week, at mid-flood and

mid-ebb tides, for a period of

4 weeks prior to the

commencement of the marine

works

 

If the water depth is

less than 3m, mid-depth

sampling only.

 

If water depth less

than 6m, mid-depth

may be omitted.

Note:  * Additional monitoring station under this Contract as per recommendation of the   Environmental Review for the Temporary Staging for Construction of the Southern      Connection (ERM, 2013)..

 

In addition to the parameters presented in Table 4.2, monitoring location/position, time, water depth, sampling depth, tidal stages, weather conditions and any special phenomena or works underway nearby should also be recorded.

4.3                                      Monitoring Methodology

Instrumentation


Table 4.3 summarizes the equipment used in the baseline water quality monitoring works.  All the monitoring equipment complied with the requirements set out in the EM&A Manual.  Copies of the calibration certificates are attached in Annex C1.

Table 4.3        Water Quality Monitoring Equipment

Equipment

Model

Qty.

Water Sampler

Kahlsico Water-Bottle Model 135DW 150

4

Multi-parameter Water Quality System

YSI 6820-C-M/YSI 6920

6

Dissolved Oxygen Meter

YSI Pro 2030

1

pH Meter

HANNA HI 8314

1

Turbidity Meter

HACH 2100Q

1

Monitoring Position Equipment

¡§Magellan¡¨ Handheld GPS Model eXplorist GC

4

DGPS Koden KGP913MK2 (1)

1

Note:

(1)   DGPS has been used for the baseline water quality monitoring for station SR4a.

A multi-parameter meters (Model YSI 6820-C-M /YSI 6920) were used to measure DO, turbidity, salinity, pH and temperature for all monitoring stations except at SR4a.

For water quality monitoring at SR4a, pH was measured by HANNA HI 8314, turbidity was measured by HACH 2100Q whilst DO, salinity and temperature were measured by YSI Pro 2030.

Operating/Analytical Procedures

At each sampling depth, two consecutive measurements of DO level, DO saturation, salinity, turbidity, pH and temperature were taken.  The probes were retrieved out of the water after the first measurement and then re-deployed for the second measurement.  Where the difference in the value between the first and second readings of each set was more than 25% of the value of the first reading, the reading was discarded and further readings were taken.  Two samples were collected for laboratory analysis of SS content.  Following collection, water samples for laboratory analysis were stored in high density polythene bottles (250ml/1L) with no preservatives added, packed in ice (cooled to 4¢XC without being frozen) and kept in dark during both on-site temporary storage and shipment to the testing laboratory.  The samples were delivered to the laboratory as soon as possible and the laboratory determination works were started within 24 hours after collection of the water samples.  Sufficient volume of samples was collected to achieve the detection limit.

Laboratory Analytical Methods

The testing of all parameters for all stations except SR4a was conducted by Wellab Ltd. (HOKLAS Registration No.083) whilst that for station SR4a was conducted by ALS Technichem (HK) Pty Ltd. (HOKLAS Registration No. 066).  Comprehensive quality assurance and control procedures were in place in order to ensure quality and consistency in results.  The testing method and reporting limit are provided in Table 4.4.

Table 4.4        Methods for Laboratory Analysis for Water Samples

Determinant

Instrumentation

Analytical Method

Reporting Limit

Suspended Solids (SS)

Weighing

APHA 17e 2540D

0.5 mg/L (1)

4.4                                      QA/QC Requirements

 

Calibration of In Situ Instruments

 

All in situ monitoring instruments were checked, calibrated and certified by a laboratory accredited under HOKLAS or other international accreditation scheme before use, and subsequently re-calibrated at 3 monthly intervals throughout all stages of the water quality monitoring programme.  Responses of sensors and electrodes were checked with certified standard solutions before each use.  Wet bulb calibration for a DO meter was carried out before measurement at each monitoring event.

 

For the on site calibration of field equipment (Multi-parameter Water Quality System), the BS 1427:2009, "Guide to on-site test methods for the analysis of waters" was observed.

 

Sufficient stocks of spare parts were maintained for replacements when necessary.  Backup monitoring equipment was also being made available so that monitoring can proceed uninterrupted even when some equipment was under maintenance, calibration, etc.

Decontamination Procedures

 

Water sampling equipment used during the course of the monitoring programme was decontaminated by manual washing and rinsed clean seawater/distilled water after each sampling event.  All disposal equipment was discarded after sampling.

Sampling Management and Supervision

 

All sampling bottles were labeled with the sample I.D (including the indication of sampling station and tidal stage e.g. IS1_me_a), laboratory number and sampling date.  Water samples were dispatched to the testing laboratory for analysis as soon as possible after the sampling. All samples were stored in a cool box and kept at less than 4¢XC but without frozen.  All water samples were handled under chain of custody protocols and relinquished to the laboratory representatives at locations specified by the laboratory.  The laboratory determination works were started within 24 hours after collection of water samples.

Quality Control Measures for Sample Testing

 

The samples testing were performed by Wellab Ltd. and ALS Technichem (HK) Pty Ltd.  The following quality control programme was performed by the laboratories for every batch of 20 samples:

 

Ÿ   One method blank; and

Ÿ   One set of quality control (QC) samples (including method QC and sample duplicate).

The QA/QC results are attached in Annex C2.

4.5                                      Baseline Monitoring Results

Baseline water quality monitoring was conducted between 6 and 31 October 2011 for all monitoring stations, except for station SR4a for which monitoring was conducted between 29 August and 24 September 2013.  The monitoring results are shown in Annex C3.  Graphical presentation of water quality at the monitoring stations is given in Annex C4.  Detailed weather conditions at the monitoring locations during the baseline monitoring period are shown in Annex F.  The monitoring schedule is shown in Annex E.

During the baseline monitoring period, no marine construction works were observed in the vicinity of all monitoring stations.  The baseline monitoring results are thus considered representative of the ambient water quality.

4.6                                      Action and Limit Levels

The Action and Limit Levels for DO, SS and turbidity are determined in accordance with requirements set out in the EM&A Manual which are summarized in Table 4.5.

Table 4.5        Action and Limit Levels for Water Quality

Parameter (unit)

Water Depth

Action Level

Limit Level

Dissolved Oxygen (mg/L) (surface, middle and bottom

Surface and Middle

5%-ile of baseline data

4mg/L except 5mg/l for FCZ or 1%-ile of baseline data

Bottom

5%-ile of baseline data

2mg/L or 1%-ile of baseline data

 

Turbidity (NTU)

Depth average

95%-ile of baseline data and 120% of upstream control station¡¦s turbidity at the same tide of the

same day

 

99%-ile of baseline and 130% of turbidity at the upstream control

station at the same tide of same day

SS (mg/L)

Depth average

95%-ile of baseline data and 120% of upstream control station¡¦s SS at the

same tide of the same day

99%-ile of baseline and 130% of SS at the upstream control station at the same tide of same day

Notes:

(1)   Depth-averaged is calculated by taking the arithmetic means of reading of all three depths

(2)   For DO, non-compliance of the water quality limit occurs when monitoring result is lower that the limit.

(3)   For SS & turbidity non-compliance of the water quality limits occur when monitoring result is higher than the limits.           

The calculated Action and Limit levels are shown in Table 4.6.

 

Table 4.6        Action and Limit Levels for Water Quality

Parameter (unit)

Water Depth

Action Level

Limit Level

Dissolved Oxygen (mg/L) (surface, middle and bottom

 

Surface and Middle

5.0

4.2 except 5 for FCZ

 

Bottom

4.7

 

3.6

Turbidity (NTU)

Depth average

27.5 and 120% of upstream control station¡¦s turbidity at the same tide of the

same day

 

47.0 and 130% of turbidity at the upstream control

station at the same tide of same day

SS (mg/L)

Depth average

23.5 and 120% of upstream control station¡¦s SS at the

same tide of the same day

34.4 and 130% of SS at the upstream control station at the same tide of same day

Notes:

(1)   Depth-averaged is calculated by taking the arithmetic means of reading of all three depths

(2)   For DO, non-compliance of the water quality limit occurs when monitoring result is lower that the limit.

(3)   For SS & turbidity non-compliance of the water quality limits occur when monitoring result is higher than the limits.           

Table 4.7        Event/ Action Plan for Water Quality

 

Event

ET Leader

         IEC

 SOR

             Contractor

Action level being exceeded by one sampling day

Repeat in situ measurement on next day of exceedance to confirm findings;

 

Identify source(s) of impact;

 

Inform IEC, contractor and SOR;

 

Check monitoring data, all plant, equipment and Contractor's working methods.

 

Check monitoring data submitted by ET and Contractor¡¦s working methods.

Confirm receipt of notification of non-compliance  in writing;

 

Notify Contractor.

Inform the SOR and confirm notification of the non-compliance  in writing;

 

Rectify unacceptable practice;

 

Amend working methods if appropriate.

Action level being exceeded by two or more  consecutive sampling days

Repeat measurement on next day of exceedance to confirm findings;

 

Identify source(s) of impact;

 

Inform IEC, contractor, SOR and EPD;

 

Check monitoring data, all plant, equipment and Contractor's working methods;

 

Discuss mitigation measures with IEC, SOR and Contractor;

 

Ensure mitigation measures are implemented;

 

Increase the monitoring frequency to daily until no exceedance of Action level;

Check monitoring data submitted by ET and Contractor¡¦s working method;

 

Discuss with ET and Contractor on possible remedial actions;

 

Review the proposed mitigation measures submitted by Contractor and advise the SOR accordingly;

 

Supervise the implementation of mitigation measures.

Discuss with IEC on the proposed mitigation measures;

 

Ensure mitigation measures are properly implemented;

 

Assess the effectiveness of the implemented mitigation measures.

Inform the Supervising Officer and confirm notification of the non-compliance  in writing;

 

Rectify unacceptable practice;

 

Check all plant and equipment and consider changes of working methods;

 

Submit proposal of additional mitigation measures to SOR within 3 working days of notification and discuss with ET, IEC and SOR;

 

Implement the agreed mitigation measures.

Limit level being exceeded by one sampling day

Repeat measurement on next day of exceedance to confirm findings;

 

Identify source(s) of impact;

 

Inform IEC, contractor, SOR and EPD;

 

Check monitoring data, all plant, equipment and Contractor's working methods;

 

Discuss mitigation measures with

IEC, SOR and Contractor;

Check monitoring data submitted by ET and Contractor¡¦s working method;

 

Discuss with ET and Contractor on possible remedial actions;

 

Review the proposed mitigation measures submitted by Contractor and advise the SOR accordingly.

Confirm receipt of notification of failure in writing;

 

Discuss with IEC, ET and Contractor on the proposed mitigation measures;

 

Request Contractor to review the working methods.

Inform the SOR and confirm notification of the non-compliance  in writing;

 

Rectify unacceptable practice;

 

Check all plant and equipment and consider changes of working methods;

 

Submit proposal of mitigation measures to SOR within 3 working days of notification and discuss with ET, IEC and SOR.

 

 

Limit level being exceeded by two or more consecutive sampling days

Repeat measurement on next day of exceedance to confirm findings;

 

Identify source(s) of impact;

 

Inform IEC, contractor, SOR and EPD;

 

Check monitoring data, all plant, equipment and Contractor's working methods;

 

Discuss mitigation measures with  IEC, SOR and Contractor;

 

 

Ensure mitigation measures are implemented;

 

Increase the monitoring frequency to daily until no exceedance of Limit level for two consecutive days;

Check monitoring data submitted by ET and Contractor¡¦s working method;

 

Discuss with ET and Contractor on possible remedial actions;

 

Review the Contractor¡¦s mitigation measures whenever necessary to assure their effectiveness and advise the SOR accordingly;

 

Supervise the implementation of mitigation measures.

Discuss with IEC, ET and Contractor on the proposed mitigation measures;

 

Request Contractor to critically review the working methods;

 

Make agreement on the mitigation measures to be implemented;

 

Ensure mitigation measures are properly implemented;

 

Consider and instruct, if necessary, the Contractor to slow down or to stop all or part of the construction activities until no exceedance of Limit level.

Take immediate action to avoid further exceedance;

 

Submit proposal of mitigation measures to SOR within 3 working days of notification and discuss with ET, IEC and SOR;

 

Implement the agreed mitigation measures;

 

Resubmit proposals of mitigation measures if problem still not under control;

 

As directed by the Supervising Officer, to slow down or to stop all or part of the construction activities until no exceedance of Limit level.

 


5                                             Ecology

5.1                                      Baseline Walk-over Survey

Baseline walk-over survey was carried out in September 2013 to confirm the existing ecological conditions with reference to the habitat maps presented in the approved EIA Report of the Project.  In accordance with requirements of the EM&A Manual, no detailed ecological surveys of flora and fauna were undertaken for the baseline walk-over survey.

5.1.1                               Observations

With reference to the habitat categorization in the approved EIA report, habitats were classified into following ten (10) types (please also refer to Table 5.1):

Mixed Woodland

In this walk over survey mixed woodland refer to both secondary woodland and mature plantation woodland with reasonable proportion of native species and typical woodland flora profile.

Tall Shrubland

Tall shrubland habitat is densely populated with a mix of native tree and shrubby plant species.

Shrubby Grassland

The shrubby grassland is dominated by herbaceous ferns and grass with shrubs and tree species that are patchily distributed on the hill-slopes within the Study area. 

Salt Marsh

Salt Marsh is those low-lying wet land that is influenced by saltwater.

Plantation

In this walk over survey, plantation refers to artificial planting area which included man-made slope and roadside plantation for landscape and ornamental use.

Cultivated Field

Cultivated field includes both active, inactive cultivation fields and orchards.

Mangrove

Mangrove refers to coastal vegetation which dominated by mangrove and mangrove associated species.

Wasteland

Wasteland is an open field which has dominated by weeds and pioneer species.

Watercourse

Watercourse included both natural stream and modified stream.

Developed Area

Typical developed areas within the Study area are the Airport Railway Deport, North Lantau Highway and Pak Mong Village.

Table 5.1        Types of Habitats observed in Walk-over Survey

Mixed Woodland

Tall Shrubland

Shrubby Grassland

Salt Marsh

Plantation

Cultivated Field

Mangrove

Wasteland

Watercourse

Developed Area

5.1.2                               Results

Habitats within Study Area

The updated habitat map is presented in Figure 5.1.  Larger area of tall shrubland was identified within the Study area.  It is believed that they are developed from previous shrubby grassland identified in approved EIA.  Woodland behind Pak Mong Village was defined as plantation woodland in previous EIA.  In this walk-over survey, both mature native species and fruit tree species are well developed into typical woodland profile.  Therefore, it is now classified as mixed woodland.  Some of the orchard area and farmland are now invaded by self-seeded plant indicating its inactive status.  However, according the approved EIA report both inactive and active are categorized as cultivated land.  Thus only those believed to be abandoned and developed into a stage that can fit the description of another types of habitat mentioned above will be shown in the updated habitat map.

It should be noted that mangrove area increased along the inner bay of Tai Ho Wan.

Habitats within Project Area

Habitat types within the Project area are similar to the approved EIA report except some of the man-made slope and landscape area that previously defined as developed area are now classified as plantation because of its vegetation coverage and maturity of development.


 

Flora Species of Conservation Interest

This walk-over survey also confirmed the existence of the flora species of conservation interest according to the figure ¡§Location of Species of Conservation Interest Recorded in North Lantau between 2003 to 2009¡¨ in approved EIA report.  Most of them can be found within the Study area except those grown in some inaccessible area (e.g. fence off area).

5.2                                      Baseline Dolphin Monitoring

Baseline dolphin monitoring was undertaken at Northwest Lantau (NWL) and Northeast Lantau (NEL) under the Chinese White Dolphin (CWD) Service Contract No. HY/2011/02 for a period of three months prior to the commencement of the Contract.  The baseline line-transect vessel surveys for dolphin monitoring were conducted in September, October and November 2011 as shown in Table 5.2.  Location of dolphin transect survey is presented in Figure 5.2.  Detailed monitoring results are presented in Annex D. 

Table 5.2        Date of Baseline Dolphin Monitoring

No.

Date

Location

1

05/09/2011

W LANTAU + NW LANTAU

2

07/09/2011

NW LANTAU + NE LANTAU

3

16/09/2011

NW LANTAU + NE LANTAU

4

23/09/2011

W LANTAU + NW LANTAU

5

06/10/2011

NE LANTAU + NW LANTAU

6

10/10/2011

NW LANTAU +NE LANTAU

7

13/10/2011

NE LANTAU

8

17/10/2011

W LANTAU + NW LANTAU

9

28/10/2011

NW LANTAU + W LANTAU

10

01/11/2011

NW LANTAU +NE LANTAU

11

02/11/2011

W LANTAU + NE LANTAU

12

05/11/2011

NW LANTAU + NE LANTAU

13

06/11/2011

NE LANTAU

14

07/11/2011

NW LANTAU + W LANTAU

Notes:

* NW Lantau = Northwest Lantau Survey Area, NE Lantau = Northeast Lantau Survey Area, W Lantau = West Lantau

In total, 112 groups of Chinese White Dolphins, numbering 413 individuals, were observed during the three-month survey.  Most of them were sighted in the West Lantau (WL) and Northwest Lantau (NWL) regions.

Major findings along and near the future alignments of HKLR and TM-CLKL as well as the reclamation site of HKBCF (collectively called ¡§the Site¡¨ below) are summarized as follows:

Ÿ   Dolphins were sighted but not in high concentration near the Site;

Ÿ   Several large dolphin aggregations were seen near the Site;

Ÿ   Several grids had moderate to high dolphin density near the Site;

Ÿ   Several mother-calf pairs were recorded (near alignments of HKLR and TM-CLKL only);

Ÿ   Several feeding activities were sighted along and near the Site; and

Ÿ   Two fishing boat-associated sightings were made near the Site.

Through photo-identification work, 96 individuals were identified from 182 sightings.  Some were sighted over three times during the three-month survey, indicating their frequent use of Hong Kong waters.  Many of them were year-round residents and some were accompanied by calves.  Ranging pattern developed showed that most of the dolphins ranged across the three survey areas including the HZMB work areas.

5.2.1                               Determination of Action and Limit Levels for Dolphin Monitoring

Vessel-based Line-transect Survey Methodology

According to the requirement of the EM&A Manual, dolphin monitoring programme should cover all transect lines in NEL and NWL survey areas twice per month throughout the entire construction period.  

 

The survey team used standard line-transect methods (Buckland et al. 2001) to conduct the systematic vessel surveys.  For each monitoring vessel survey, a 15-m inboard vessel (Standard 31516) with an open upper deck (about 4.5 m above water surface) will be used to make observations from the flying bridge area.

 

Two experienced observers (a data recorder and a primary observer) made up the on-effort survey team, and the survey vessel will transit different transect lines at a constant speed of 13-15 km per hour.  The data recorder will search with unaided eyes and fill out the datasheets, while the primary observer will search for Chinese white dolphins continuously through 7 x 50 marine binoculars.  Both observers will search the sea ahead of the vessel, between 270o and 90o (in relation to the bow, which is defined as 0o).  One to two additional experienced observers will be available on the boat to work in shift (i.e. rotate every 30 minutes) in order to minimize fatigue of the survey team members. 

 

During on-effort survey periods, the survey team will record effort data including time, position (latitude and longitude), weather conditions (Beaufort sea state and visibility), and distance traveled in each series (a continuous period of search effort) with the assistance of a handheld GPS (Garmin eTrex Legend).

 

Data including time, position and vessel speed will also automatically and continuously be logged by handheld GPS throughout the entire survey for subsequent review.

When dolphins are sighted, the survey team will end the survey effort, and immediately record the initial sighting distance and angle of the dolphin group from the survey vessel, as well as the sighting time and position.  Then the research vessel will be diverted from its course to approach the animals for species identification, group size estimation, assessment of group composition, and behavioural observations.  The perpendicular distance (PSD) of the dolphin group to the transect line will be later calculated from the initial sighting distance and angle.

 

Survey effort being conducted along the parallel transect lines that are perpendicular to the coastlines will be labeled as ¡§primary¡¨ survey effort, while the survey effort conducted along the connecting lines between parallel lines will be labeled as ¡§secondary¡¨ survey effort.

Data Analysis (Dolphin Encounter Rate)

 

Encounter rates of Chinese white dolphins (number of on-effort sightings per 100 km of survey effort, and total number of dolphins sighted on-effort per 100 km of survey effort) will be calculated in NEL and NWL survey areas in relation to the amount of survey effort conducted during each month of monitoring survey.  Dolphin encounter rates will be calculated for comparison between the baseline monitoring and impact monitoring results

 

For the HZMB baseline monitoring results, the encounter rates were calculated using primary survey effort alone (i.e. effort conducted along parallel transect lines that were perpendicular to the coastlines).  Only data collected under Beaufort 3 or below condition would be used for encounter rate analysis.  The average encounter rate of sightings (STG) and average encounter rate of dolphins (ANI) were deduced based on the encounter rates from six events during the baseline period (i.e. six sets of line-transect surveys in North Lantau) using the following formulae: 

 

Total No. of On-effort Sightings

Encounter Rate (STG) = ---------------------------------------------------- x 100

                         Total Amount of Survey Effort (km)

 

Total No. of Dolphins from All On-effort Sightings

Encounter Rate (ANI) = -------------------------------------------------------------------- x 100

                              Total Amount of Survey Effort (km)

 

These encounter rates will be used for the implementation of Event and Action Plan to examine whether the Action Level or Limit Level should be triggered from the comparison of encounter rates between baseline and impact phase quarterly monitoring periods.

 

Dolphin Encounter Rates during Baseline Period

 

During the present three-month study period, the encounter rates of Chinese White Dolphins deduced from the survey effort and on-effort sighting data from the primary transect lines under favourable conditions (Beaufort 3 or below) from each of the survey areas are shown in Table 5.3.

Table 5.3        Dolphin Encounter Rates (Sightings Per 100 km of Survey Effort) during the Baseline Monitoring Period (September - November 2011)

Survey Area

Dolphin Monitoring

Encounter rate (STG)
(no. of on-effort dolphin sightings per 100 km of survey effort)

Encounter rate (ANI)
(no. of dolphins from all on-effort sightings per 100 km of survey effort)

Primary Lines Only

Primary Lines Only

Northeast  Lantau

Set 1

3.34

3.34

Set 2

0.00

0.00

Set 3

3.02

15.11

Set 4

5.92

14.79

Set 5

13.76

73.39

Set 6

9.93

26.49

Average from the six sets

6.00 ¡Ó 5.05

22.19 ¡Ó 26.81

Northwest Lantau

Set 1

1.39

2.77

Set 2

16.57

55.25

Set 3

5.24

24.48

Set 4

8.45

35.47

Set 5

13.13

86.30

Set 6

14.33

83.69

Average from the six sets

9.85 ¡Ó 5.85

44.66 ¡Ó 29.85

Event and Action Plan for Dolphin Impact Monitoring

To define the Action Level (AL) and Limit Level (LL) in comparison with the baseline dolphin encounter rate, the seasonal fluctuation of dolphin encounter rate in NWL and NEL were considered by comparing dolphin encounter rates across the four seasons in order to take the natural fluctuation of dolphin occurrence into account. 

 

Notably, the natural fluctuation among different seasons can differ by as much as 30%, and in a few extreme cases up to 40-60% upon review of dolphin historical data in North Lantau waters.

 

Therefore, the approach of 30% and 60% percentage reduction to define the AL and LL, respectively, is reasonable to determine whether the construction activities of TM-CLKL project have caused real significant impact on dolphin occurrence, instead of triggering false alarms prematurely.  Although the exact percentages (30%/60%) for the AL and LL are set somewhat arbitrarily, this is based on careful consideration of the natural fluctuation of dolphin occurrences among different seasons as explained above.

 

The proposed AL and LL are shown in Tables 5.4 and 5.5:

Table 5.4        Action Level and Limit Level for Dolphin Impact Monitoring

 

North Lantau Social Cluster

 

NEL

NWL

Action Level

STG < 70% of baseline &
ANI < 70% of baseline

STG < 70% of baseline &
ANI < 70% of baseline

Limit Level

STG < 40% of baseline &
ANI < 40% of baseline

STG < 40% of baseline &
ANI < 40% of baseline

Notes:

1.            STG means quarterly encounter rate of number of dolphin sightings, which is 6.00 in NEL and 9.85 in NWL during the baseline monitoring period

2.            ANI means quarterly encounter rate of total number of dolphins, which is 22.19 in NEL and 44.66 in NWL during the baseline monitoring period

3.            AL will be trigger if either NEL or NWL fall below the criteria; LL will be triggered if both NEL and NWL fall below the criteria.

Table 5.5        Derived Value of Action Level (AL) and Limit Level (LL)

 

North Lantau Social Cluster

 

NEL

NWL

Action Level

STG < 4.2 & ANI< 15.5

STG < 6.9 & ANI < 31.3

Limit Level

STG < 2.4 & ANI <8.9

STG < 3.9 & ANI <17.9

Notes:

1.            AL will be trigger if either NEL or NWL fall below the criteria; LL will be triggered if both NEL and NWL fall below the criteria.

Should non-compliance of the criteria occur, action in accordance with the Event and Action Plan, as provided in Table 5.6 should be carried out.

 


Table 5.6        Implementation of Event-Action Plan for Dolphin Monitoring

Event

ET Leader

IEC

SOR

Contractor

Action Level

1.   Repeat statistical data analysis to confirm findings;

 

2.   Review all available and relevant data, including raw data and statistical analysis results of other parameters covered in the EM&A, to ascertain if differences are as a result of natural variation or previously observed seasonal differences;

 

3.   Identify source(s) of impact;

 

4.   Inform the IEC, SOR and Contractor;

 

5.   Check monitoring data.

 

6.   Review to ensure all the dolphin protective measures are fully and properly implemented and advise on additional measures if necessary.

 

1.  Check monitoring data submitted by ET and Contractor;

 

2.  Discuss monitoring results and findings with the ET and the Contractor.

1.   Discuss monitoring with the IEC and any other measures proposed by the ET;

 

2.   If SOR is satisfied with the proposal of any other measures, SOR to signify the agreement in writing on the measures to be implemented.

1.  Inform the SOR and confirm notification of the non-compliance in writing;

 

2.  Discuss with the ET and the IEC and propose measures to the IEC and the SOR;

 

3.  Implement the agreed measures.

Limit Level

1.   Repeat statistical data analysis to confirm findings;

2.   Review all available and relevant data, including raw data and statistical analysis results of other parameters covered in the EM&A, to ascertain if differences are as a result of natural variation or previously observed seasonal differences;

3.   Identify source(s) of impact;

4.   Inform the IEC, ER/SOR and Contractor of findings;

5.   Check monitoring data;

6.   Repeat review to ensure all the dolphin protective measures are fully and properly implemented and advise on additional measures if necessary;

7.   If ET proves that the source of impact is caused by any of the construction activity by the works contract, ET to arrange a meeting to discuss with IEC, ER/SOR and Contractor the necessity of additional dolphin monitoring and/or any other potential mitigation measures (e.g., consider to modify the perimeter silt curtain or consider to control/temporarily stop relevant construction activity etc.) and submit to IEC a proposal of additional dolphin monitoring and/or mitigation measures where necessary.

 

1.  Check monitoring data submitted by ET and Contractor;

2.  Discuss monitoring results and findings with the ET and the Contractor;

3.  Attend the meeting to discuss with ET, ER/SOR and Contractor the necessity of additional dolphin monitoring and any other potential mitigation measures;

4.  Review proposals for additional monitoring and any other mitigation measures submitted by ET and Contractor and advise ER/SOR of the results and findings accordingly;

5.  Supervise / Audit the implementation of additional monitoring and/or any other mitigation measures and advise ER/SOR the results and findings accordingly.

1.   Attend the meeting to discuss with ET, IEC and Contractor the necessity of additional dolphin monitoring and any other potential mitigation measures;

2.   If ER/SOR is satisfied with the proposals for additional dolphin monitoring and/or any other mitigation measures submitted by ET and Contractor and verified by IEC, ER/SOR to signify the agreement in writing on such proposals and any other mitigation measures;

3.   Supervise the implementation of additional monitoring and/or any other mitigation measures.

1.  Inform the ER/SOR and confirm notification of the non- compliance in writing;

2.  Attend the meeting to discuss with ET, IEC and ER/SOR the necessity of additional dolphin monitoring and any other potential mitigation measures;

3.  Jointly submit with ET to IEC a proposal of additional dolphin monitoring and/or any other mitigation measures when necessary;

4.   Implement the agreed additional dolphin monitoring and/or any other mitigation measures.


5.3                                      Baseline Bored Pilling Monitoring

In accordance with the EM&A Manual, baseline bored piling monitoring comprising land-based theodolite tracking, underwater noise monitoring and acoustic behavioural monitoring were undertaken in September and October 2013 before commencement of construction of the Contract.  Findings of the baseline bored pilling monitoring are presented in the following sections.

5.3.1                               Land-Based Theodolite Tracking

The objective of the land-based theodolite tracking is to monitor the movement and behaviour of Chinese White Dolphins near the bored piling works before, during and after the works in order to record and note any changes in response to the bored piling noise.  Detailed methodology, results and discussion of the baseline land-based theodolite tracking which is undertaken before commencement of construction under the Contract is presented in Annex G.  Key findings are presented below.

Survey Location and Efforts

A total of 186 hours and 28 minutes were spent during the 30 days of effort from 9 September to 14 October 2013 for the baseline land-based theodolite tracking.  Dolphins were successfully tracked from the land-based station on 2 of 30 days of effort, and a total of three (3) dolphin groups were tracked.  A total of 3,053 vessels of 16 different types were tracked with the majority being transportation vessels. 

Location of the Pak Mong Station where monitoring was undertaken is provided in Figure 5.3.

Key Findings

Amongst the three dolphin tracks recorded during the baseline monitoring, only one met the conditions for analysis (please refer to Annex G for details on methodology of data analysis).  This group was tracked for 47 minutes and 37 seconds near Siu Ho Wan (ie approximately 1.5-2.0 km from the alignment of the Southern Connection Viaduct Section; Figures 5.4 and 5.5), during which three (3) vessels approached within 500 meters (fishing boat = 1, dumping guide boats = 2).  A maximum of one (1) boat was present at any time, for a total of 10 minutes of interaction time for all three boats.  The mean speed of the dolphin group over the duration of the track was 9.02 km/hr, reorientation rate was 156.1 ˚/surfacing, linearity was 0.010, and inter-breath interval was 99 seconds. 

Notably, the single track analysed for the present Study was located near Siu Ho Wan and Shum Shui Kok, at least 2km from the Pak Mong Station and at a distance from the Southern Connection Viaduct Section.  Therefore, the movement pattern of dolphins at this great distance away from the potential impact area may not provide indicative information to establish the baseline condition for the EM&A programme. 

From the results presented here, it is clear that the Study area is not frequently used by dolphins even before commencement of construction of the Southern Connection Viaduct Section.  In fact, there are multiple lines of evidence to support that dolphins rarely occur in the area near the Southern Connection Viaduct Section in the past and present:

l   Review of Hong Kong Cetacean Research Project (HKCRP) long-term monitoring data on Chinese White Dolphins indicated that very few dolphins have occurred in this area in the past.  Out of the 927 dolphin sightings made in NEL during 2002-2013, fewer than 10 groups were sighted in the proximity to the Southern Connection Viaduct Section (Figure 5.6).

l   Under the same bored piling monitoring programme for the TM-CLKL, concurrent intensive surveys were conducted to examine dolphin acoustic behaviour in NEL area between 26 September and 25 October 2013.  Despite a large amount of search effort spent in this area during the 30-day period, no dolphin was sighted in the proximity to the TM-CLKL alignment at all, and most dolphin sightings were made in the northern portion of the survey area (Figure 5.7).

l   For the same bored piling monitoring programme, passive acoustic monitoring was also conducted to detect dolphin presence 24 hours a day, by deploying an Ecological Acoustic Recorder (EAR) adjacent to the bridge alignment from 27 September to 26 October 2013.  Results indicated that dolphin acoustic activity near the TM-CLKL alignment was much lower than a control site near Lung Kwu Chau.  The Study concluded that the lack of dolphin whistles recorded and the sparse detections of clicks was an indicator that the area near the TM-CLKL alignment was likely not used very much for socializing or regular foraging by the dolphins.

In summary, dolphins rarely occur along or near the Southern Connection Viaduct Section in the past and present.  This may be related to the high level of human activity, but more likely is driven by other factors such as the absence of prey, or the shallowness of seabed in this area.  If this area has a naturally low density of dolphins, then the overall effect of construction activities on dolphins is likely to be low, which confirm the prediction from the original EIA study for the TM-CLKL Project. 

Variation to the Event and Action Plan

According to Section 6.5 of the EM&A Manual, the Action and Limit Levels as well as the Event and Action Plan for ecology should be proposed using the baseline monitoring data.  The response variables for dolphin movement patterns (ie mean leg speed, mean inter-breath interval, reorientation rate and linearity) and dolphin behaviour (five different behavioural states) should be assessed under the Event and Action Plan, and these variables should be recorded during both baseline and construction phase monitoring works.  Departures of any of these variables between baseline and construction phases by a certain percentage of difference would trigger the Action and Limit Levels.

However, due to the paucity of dolphin sightings and the availability of a single track for analysis from the present 30-day land-based theodolite tracking works, it is impossible to reliably establish the baseline values for the various response variables.  In addition, as dolphins rarely occur in this area as discussed above, it is expected that such rare occurrence of dolphins would persist during the construction phase of the Contract.  Without appropriate baseline information established for the behaviour and movement of Chinese White Dolphins, it is decided that any Event and Action Plan cannot be properly implemented for the land-based theodolite tracking during impact monitoring, and therefore it would rely on the implementation of Event and Action Plan on dolphin acoustic behaviour to monitor/safeguard dolphins from the potential impacts of the bored piling works.  Nevertheless, it is important to conduct the construction phase and post-construction phase monitoring on behaviour and movements of Chinese White Dolphin through land-based theodolite tracking to confirm that they are not seriously affected by the construction works if they are present.

5.3.2                               Underwater Noise Monitoring

For the underwater noise monitoring, the primary objectives were to measure and characterize the following:

l   Baseline ambient noise levels during the pre-construction phase of development; and

l   Industrial noise levels associated with bored piling activities during the construction phase.

Detailed methodology, results and discussion of the baseline underwater noise monitoring which is undertaken before commencement of construction under the Contract is presented in Annex H.  Key findings are presented below.

Survey Location and Efforts

Thirty days of underwater noise monitoring were conducted between 26 September and 25 October 2013 before commencement of construction of the Southern Connection Viaduct Section.  To characterize the local soundscape, underwater sound data collection were conducted mostly in the northeastern waters of Lantau Island where bored piling activities in association with construction of the Southern Connection Viaduct Section will occur.  Sound measurements were made at various distances from six bored piling sites along the TM-CLKL alignment (Figure 5.8) to allow estimation of a simple acoustic propagation model for the region. 

Key Findings

A total of 472 underwater acoustic recordings were available for the underwater noise monitoring.  After data quality checking, 440 recordings were selected for subsequent noise analyses.  The primary reason for data exclusion, accounting for 32 recordings, were user-selected gain changes that occurred mid-recording and introduced high-frequency (10¡V20 kHz) artifacts that could bias the acoustic results with electronic noise.

The selected data were analyzed in terms of both a ¡§wideband¡¨ frequency range of 30 Hz to 40 kHz and a ¡§dolphin-sensitive¡¨ frequency range of 400 Hz to 12.5 kHz.  Mean bandlevel across all recordings was 116.71 ¡Ó 6.29 dB re 1 £gPa for the wideband case and 112.27 ¡Ó 6.36 dB re 1 £gPa for the dolphin band case, where ¡§¡Ó x.xx¡¨ refers to one standard deviation from the mean and indicates the degree of variability in the measurements.  According to observer logs and confirmed in the acoustic records, vessel traffic is the greatest contributor to the local soundscape.  Bandlevels were not substantially affected by wind speed or tidal height (tidal current), likely due to generally light winds and recording system design, respectively.

Of the 440 recordings analyzed, 122 recordings contained dolphin vocalizations.  Average bandlevel across these recordings was 118.44 ¡Ó 5.88 dB re 1 £gPa and 114.94 ¡Ó 5.26 dB re 1 £gPa for the wideband frequency range and dolphin band, respectively (Figure 5.9).  By comparison, recordings without dolphin vocalizations (318 recordings) had average bandlevels of 116.04 ¡Ó 6.34 dB re 1 £gPa and 111.24 ¡Ó 6.46 dB re 1 £gPa for wide and dolphin frequency bands, respectively.  Since mean bandlevel was calculated across the entire recording and the bandwidth as indicated, bandlevels for the recordings containing dolphin vocalizations may not be representative of received levels of individual dolphin vocalizations, and likely contain other sound sources such as vessels and should thus be interpreted with caution.  However, the large sample sizes and over 3 dB difference in average bandlevels, in particular in the dolphin band, suggest that, when vocalizing, dolphins can contribute significantly to the soundscape.

Variability of soundscape with time is observed with increased sound levels during daylight hours (Figure 5.10).  However, a bias might be present due to the relatively small sample sizes outside daytime hours (n=82, as compared to the sample size in daytime hours (n=358)), but increased sound levels during daylight hours may also be attributed to increased vessel traffic, fishing, construction, and other anthropogenic activity more likely to occur during the day.

It should be noted the development of an Event and Action Plan is not required under the EM&A Manual for the underwater noise monitoring.  However, results obtained from this Study, in conjunction with the concurrent dolphin acoustic behavioural and land-based theodolite tracking studies, would provide guidance with respect to mitigation for the resident dolphin population during the impact monitoring phase.

5.3.3                               Acoustic Behavioural Monitoring

The primary objective of the acoustic behavioural monitoring of Chinese White Dolphins was to investigate their acoustic behaviour in response to bored piling sites during both baseline and construction phases of the Southern Connection Viaduct Section in order to understand whether any observed differences in acoustic behaviour of dolphins may represent a reaction to the bored piling works.

Detailed methodology, results and discussion of the baseline acoustic behavioural monitoring which is undertaken before commencement of construction under the Contract is presented in Annex H.  Key findings are presented below.

Survey Location and Efforts

The acoustic behavioural monitoring was conducted concurrently with the underwater noise monitoring between 26 September and 26 October 2013 before commencement of construction of the Southern Connection Viaduct Section.  The acoustic behavioural monitoring was undertaken using both dipping hydrophone and passive acoustic monitoring by ecological acoustic recorders (EARs).

Acoustic behavioural monitoring by dipping hydrophone was undertaken mostly in the northeastern waters of Lantau Island where the bored piling activities will occur.  For this Study, the research vessel followed a predefined route for systematic search effort in Northeast Lantau region to cover the area overlapped with the alignment of the Southern Connection Viaduct Section (Figure 5.11), where dolphins will be potentially disturbed by the bored piling works during the construction phase.  The survey also covered part of Northwest Lantau waters as control sites, where dolphins were likely encountered for acoustic data collection but would not be disturbed by the bored piling activities (eg Sha Chau, Lung Kwu Chau and Black Point).

For passive acoustic monitoring, the EARs were deployed at following two locations (Figure 5.11):

l   Within 500 m of the bridge alignment (Site C1); and

l   A control site between Sha Chau and Lung Kwu Chau (Site C2), a less disturbed site relatively far away from the alignment of the Southern Connection Viaduct Section.  

Key Findings

Acoustic Behavioural Monitoring using Dipping Hydrophones

A total of 629 recording minutes were made during the baseline acoustic monitoring period.  Figure 5.12 shows the number of recording minutes summed for each day, as well as the number of sightings per day.  Recordings were obtained on all but 8 days of the 30-day period.  The daily number of 5-minute recordings ranged between 0 and 15 (mean = 4.4, stdv = 4.1) and the daily number of minutes recorded was between 0 and 73.4 (mean = 21.0, stdv = 20.1).  Whistling and clicking rates were determined for all recordings (n =122).  Figure 5.13 shows the daily rate of click and whistle production recorded. The mean daily whistling rate was 2.8 whistles/min (stdv = 3.9) and the mean click production rate was 165.9 clicks/min (stdv = 100.0).

Findings from the baseline acoustic behavioural monitoring using dipping hydrophones indicate that acoustic activity of Chinese White Dolphins tended to increase with group size and was highest during socializing periods.  There was a gradual rise in the click production rate throughout the day, peaking in the afternoon period between 14:00 and 15:59.  This suggests that the afternoon could be a time of increased foraging or socializing for dolphins in this area.  A large difference in the occurrence of whistling was observed between Zones 1a (to the west of the construction area) and 1b (including the construction area).  This suggests that, at least during daytime hours when the data were obtained, Zone 1a may be used differently than Zone 1b by the dolphins.  A proportionately greater whistling rate in Zone 1b suggests more emphasis on social behaviors.  On the other hand, clicking rates were equivalent between zones, suggesting that dolphin vigilance and foraging effort may be similar in the two zones.

Summary of data collected from the baseline acoustic behavioural monitoring using dipping hydrophones is presented in Table 5.7.

Table 5.7        Values of the two response variables of dolphin acoustic behaviour collected by calibrated hydrophone (mean clicks and whistles per minutes) by size of group, behavioural state and time of day during baseline period

 

Mean number of clicks per minute ( ¡Ó s.d.)

 

Mean number of whistles per minute ( ¡Ó s.d.)

 

Group Size

 

 

1 dolphins

169.74 ¡Ó 194.88 (n=10)

2.89 ¡Ó 5.21 (n=10)

2-5 dolphins

161.46 ¡Ó 160.61 (n=86)

3.14 ¡Ó 6.54 (n=86)

6-9 dolphins

207.25 ¡Ó 157.17 (n=35)

5.64 ¡Ó 9.91 (n=35)

 

 

 

Behavioural State

 

 

Feeding

165.09 ¡Ó 118.49 (n=18)

2.71 ¡Ó 6.67 (n=18)

Milling

183.73 ¡Ó 182.09 (n=123)

3.83 ¡Ó 7.63 (n=123)

Socializing

294.63 ¡Ó 159.98 (n=4)

3.05 ¡Ó 3.33 (n=4)

Traveling

119.98 ¡Ó 81.82 (n=22)

4.98 ¡Ó 8.77 (n=22)

 

Time of day

 

 

08:00-09:59

100.83 ¡Ó 77.23 (n=5)

2.30 ¡Ó 4.35 (n=5)

10:00-11:59

155.65 ¡Ó 120.40 (n=35)

4.77 ¡Ó 9.59 (n=35)

12:00-13:59

171.08 ¡Ó 149.02 (n=52)

2.08 ¡Ó 5.08 (n=52)

14:00-15:59

218.49 ¡Ó 241.38 (n=27)

3.88 ¡Ó 5.77 (n=27)

16:00-17:59

186.40 ¡Ó 122.57 (n=11)

7.82 ¡Ó 11.83 (n=11)

Passive Acoustic Monitoring by EARs

Dolphin signals were detected on 26 out of 30 days of EAR recordings at C1 (Southern Connection Viaduct Section alignment area).  Figure 5.14 shows the percentage of files for each day (288 recordings per day) that contained dolphin signals.  Daily dolphin acoustic activity was low, with between 0% and 4.5% of recordings containing dolphin signals any given day.  Figure 5.15 shows the number of dolphin encounters and the mean duration of encounters for each day of the deployment period.  There were a mean of 4.6 encounters per day (S.D. = 3.3) at site C1, which lasted a mean of 1.9 min (S.D. = 3.6).

Dolphin signals were detected on all 30 days of EAR recordings at Site C2 (control site near Lung Kwu Chau).  Figure 5.16 shows the percentage of files for each day (288 recordings per day) that contained dolphin signals. Daily dolphin acoustic activity was variable, with between ~1% and 28% or recordings containing dolphin signals any given day.  Figure 5.17 shows the number of dolphin encounters and the mean duration of encounters for each day of the deployment period.  There were a mean of 8.6 encounters per day (S.D. = 2.0) at site C2, which lasted a mean of 25.0 min (S.D. = 14.3).

The EAR data indicate that dolphin acoustic activity is considerably greater at site C2 (control site near Lung Kwu Chau) than at site C1 (Southern Connection Viaduct Section alignment area).  Dolphin detections at site C1 did not exhibit any temporal pattern of dolphin occurrence.  At site C2, the main temporal features were the peak in detections occurring in the morning hours between 08:00 and 9:59, followed by a comparative lull in the mid-day hours between 11:00 and 13:59.  The difference in both detection rates and temporal occurrence suggest that dolphins use sites C1 and C2 very differently.  The lack of whistles recorded and the sparse detections at Site C1 is an indicator that the area is likely not used very much for socializing or regular foraging. 

Event Action Plan

According to Section 6.5 of the EM&A Manual, the Action and Limit Levels as well as the Event Action Plan for ecology should be proposed using the baseline monitoring data.  More specifically, as described in Table 6.9 of the EM&A Manual, the Event Action Plan should be triggered when dolphin numbers and behaviour patterns recorded in the construction and post-construction monitoring are significantly lower or different than those recorded in the pre-construction monitoring.  Therefore, an Event and Action Plan should be developed to examine changes in the dolphin acoustic behaviour between baseline and impact phases of monitoring.  

To develop the Event and Action Plan (EAP) on dolphin acoustic behaviour, it is proposed to take into account of the values of two response variables (clicking and whistling rates) as a function of the size of dolphin group, their behavioural state and time of day deduced from the calibrated hydrophone data as presented in Table 5.7.  Departures of any of these variables between baseline and construction phases with a 20% difference will be of concern and should trigger the Action Level under the Event Action Plan.  If a 40% difference in any of these variables between baseline and construction phases is detected, then the Limit Level under the Event Action Plan should be triggered and immediate actions will be required.  The Action and Limit Levels of these variables are presented in Table 5.8.

In addition, the response variable for the EAR data should be the diel occurrence at the two sites (ie Impact Site C1 and Control Site C2).  However, there was no distinct diel pattern in acoustic activity of dolphins at Site C1 and there was only a weak diel pattern observed at Site C2.  As there was no distinct peak occurrence of dolphins at Site C1, the shift of peak occurrence in acoustic signal detection cannot be used as triggering mechanism for the Event and Action Plan.  Alternatively, it is proposed that if there is a 20% difference in detections occurred during the nighttime period between 19:00 and 6:59 at Site C1 (baseline percentage of detection as 54%) in the impact phase monitoring period (i.e. ≥74% or ≤34% of all detections occurred at nighttime), then the Action Level should be triggered.  On the other hand, if there is a 40% difference in detections occurred during the nighttime period between 19:00 and 6:59 at Site C1 in the impact phase monitoring period (i.e. ≥94% or ≤14% of all detections occurred at nighttime), then the Limit Level should be triggered.  However, if such 20% or 40% difference occurs at both Sites C1 and C2 (baseline percentages of detections as 54% and 53% respectively), the action or limit level should not be triggered, as the change in diel pattern of dolphin occurrence does not only occur at the site of impact (C1) but also at the control site (C2), and the changes in dolphin occurrence at both sites may not be directly to the TM-CLKL construction works.  Such review of data from Site C2 (control site between Lung Kwu Chau and Sha Chau) should be part of the review as listed in Action #2 by the ET Leader when the AL or LL is triggered as detailed in the Action and Event Plan (Table 5.9).

Table 5.8        Action Level (AL) and Limit Level (LL) for all response variables by size of group, behavioural state and time of day

 

Mean no. of clicks per minute

Mean no. of whistles per minute

Group Size

AL / LL

AL / LL

1 dolphins (20%/40% lower)

135.79 / 101.84

2.31 / 1.73

1 dolphins (20%/40% higher)

203.69 / 237.64

3.47 / 4.05

2-5 dolphins (20%/40% lower)

129.17 / 96.88

2.51 / 1.88

2-5 dolphins (20%/40% higher)

193.75 / 226.04

3.77 / 4.40

6-9 dolphins (20%/40% lower)

165.80 / 124.35

4.51 / 3.38

6-9 dolphins (20%/40% higher)

248.70 / 290.15

6.77 / 7.90

 

 

 

Behavioural State

AL / LL

AL / LL

Feeding (20%/40% lower)

132.07 / 99.05

2.17 / 1.63

Feeding (20%/40% higher)

198.11 / 231.13

3.25 / 3.79

Milling (20%/40% lower)

146.98 / 110.24

3.06 / 2.30

Milling (20%/40% higher)

220.48 / 257.22

4.60 / 5.36

Socializing (20%/40% lower)

235.70 / 176.78

2.44 / 1.83

Socializing (20%/40% higher)

353.56 / 412.48

3.66 / 4.27

Traveling (20%/40% lower)

95.98 / 71.99

3.98 / 2.99

Traveling (20%/40% higher)

143.98 / 167.97

5.98 / 6.97

 

 

 

Time of day

AL / LL

AL / LL

08:00-09:59 (20%/40% lower)

80.66 / 60.50

1.84 / 1.38

08:00-09:59 (20%/40% higher)

121.00 / 141.16

2.76 / 3.22

10:00-11:59 (20%/40% lower)

124.52 / 93.39

3.82 / 2.86

10:00-11:59 (20%/40% higher)

186.78 / 217.91

5.72 / 6.68

12:00-13:59 (20%/40% lower)

136.86 / 102.65

1.66 / 1.25

12:00-13:59 (20%/40% higher)

205.30 / 239.51

2.50 / 2.91

14:00-15:59 (20%/40% lower)

174.79 / 131.09

3.10 / 2.33

14:00-15:59 (20%/40% higher)

262.19 / 305.89

4.66 / 5.43

16:00-17:59 (20%/40% lower)

149.12 / 111.84

6.26 / 4.69

16:00-17:59 (20%/40% higher)

223.68 / 260.96

9.38 / 10.95


Table 5.9  Event and Action Plan on Dolphin Acoustic Behaviour

EVENT

ACTION

ET Leader

IEC

SO

Contractor

Action Level

With the numerical values presented in Table 5.7, when any of the response variable for dolphin acoustic behaviour recorded in the construction phase monitoring is 20% lower or higher than that recorded in the baseline monitoring (see Table5.8), or when there is a difference of 20% in dolphin acoustic signal detection at nighttime period at Site C1 only, the action level should be triggered

 

1. Repeat statistical data analysis to confirm findings;

2. Review all available and relevant data to ascertain if differences are as a result of natural variation or seasonal differences;

3. Identify source(s) of impact;

4. Inform the IEC, SO and Contractor;

5. Check monitoring data;

6. Carry out audit to ensure all dolphin protective measures are implemented fully and additional measures be proposed if necessary

 

1. Check monitoring data submitted by ET and Contractor;

2. Discuss monitoring with the ET and the Contractor;

 

 

1. Discuss with the IEC the repeat monitoring and any other measures proposed by the ET;

2. Make agreement on measures to be implemented.

 

1. Inform the SO and confirm notification of the non- compliance in writing;

2. Discuss with the ET and the IEC and propose measures to the IEC and the SO;

3. Implement the agreed measures.

Limit Level

With the numerical values presented in Table 5.7, when any of the response variable for dolphin acoustic behaviour recorded in the construction phase monitoring is 40% lower or higher than that recorded in the baseline monitoring (see Table 5.8), or when there is a difference of 40% in dolphin acoustic signal detection at nighttime at Site C1 only, the limit level should be triggered

 

1. Repeat statistical data analysis to confirm findings;

2. Review all available and relevant data to ascertain if differences are as a result of natural variation or seasonal differences;

3. Identify source(s) of impact;

4. Inform the IEC, SO and Contractor;

5. Check monitoring data;

6. Carry out audit to ensure all dolphin protective measures are implemented fully and additional measures be proposed if necessary

7. Discuss additional dolphin monitoring and any other potential mitigation measures (eg consider to temporarily stop relevant portion of construction activity) with the IEC and Contractor.

 

1. Check monitoring data submitted by ET and Contractor;

2. Discuss monitoring with the ET and the Contractor;

3. Review proposals for additional monitoring and any other measures submitted by the Contractor and advise ER accordingly.

 

1. Discuss with the IEC the repeat monitoring and any other measures proposed by the ET;

2. Make agreement on measures to be implemented.

 

1. Inform the SO and confirm notification of the non- compliance in writing;

2. Discuss with the ET and the IEC and propose measures to the IEC and the SO;

3. Implement the agreed measures.

Abbreviations: ET ¡V Environmental Team, IEC ¡V Independent Environmental Checker, SO ¡V Supervising Office


6                                             Conclusion

In accordance with the EM&A Manual of the TM-CLKL Project, baseline monitoring has been undertaken prior to commencement of the construction works of the Contract for the following baseline monitoring components:

Ÿ   Air Quality;

Ÿ   Noise;

Ÿ   Water Quality; and

Ÿ   Ecology (including baseline walk-over survey, baseline dolphin monitoring and baseline bored piling monitoring).

The baseline air quality monitoring was conducted at two (2) monitoring locations (ASR9A and ASR9C ¡V Siu Ho Wan MTRC Depot) between 18 and 31 October 2011.  Overall, the baseline air quality monitoring results are considered representative to the ambient air quality conditions of the respective sensitive receivers.  The Action and Limit Levels for air quality (ie for 1-hour and 24-hour TSP levels) were established based on the baseline monitoring results.

 

Baseline noise monitoring was conducted at the designated monitoring station NSR1 at Pak Mong Village between 18 October and 1 November 2011.  The major noise sources identified at the monitoring station are the noise from insect and bird calling.  The baseline monitoring results are considered representative of the ambient noise level.

Baseline water quality monitoring was conducted at seven (7) monitoring stations (IS(Mf)9, IS(Mf)16, IS8, SR4, SR4a, CS(Mf)3 and CS(Mf)5) between 6 and 31 October 2011, except for monitoring at station SR4a which was conducted between 29 August and 24 September 2013.  No observable pollution source was recorded at the monitoring stations and the baseline monitoring results are thus considered representative of the ambient water quality levels.  Action and Limit Levels were established for DO, SS and turbidity based on the baseline monitoring results.

 

Baseline walk-over survey was conducted on 13 and 24 September 2013 with ten (10) different types of habitats observed in the Study area.  Overall, there appeared to be no significant changes in conditions of habitats within the Study area.

 

Baseline Chinese White Dolphin monitoring was conducted in two survey areas (Northeast Lantau and Northwest Lantau) from September to November 2011.  Dolphin sightings, distribution, encounter rate, group size, habitat use, mother-calf pairs and behavior were reported.  Photo-identification and range estimation of identified individuals were also made.  Action and Limit Levels are established based on the dolphin encounter rate with due consideration on seasonal variation in dolphin abundance.

Baseline bored piling monitoring comprising land-based theodolite tracking, underwater noise monitoring and acoustic behavioural monitoring were conducted between September and October 2013 before commencement of construction of the Contract.  Action and Limit Levels as well as the Event Action Plan are established based on the baseline monitoring data obtained from the dolphin acoustic behaviour monitoring.

 


 



([1])     Agreement No. CE 35/2011 (EP) Baseline Envrionmental Monitoring for Hong Kong-Zhuhai-Macao Bridge Hong Kong Projects-Investigation.

           http://www.hzmbenpo.com/ep_docs/HKBCF_HY201002/503/Baseline_Report_Version_C.pdf

([2])     Agreement No. CE 35/2011 (EP) Baseline Envrionmental Monitoring for Hong Kong-Zhuhai-Macao Bridge Hong Kong Projects-Investigation.

           http://www.hzmbenpo.com/ep_docs/HKBCF_HY201002/503/Baseline_Report_Version_C.pdf