(I)
Document
Status
Details of Revision:
Revision |
Rev. Date |
Sections |
Amendment Source and/or Details |
A |
30 Aug 2013 |
All |
Issued for Approval |
B |
23 Sep 2013 |
All |
Revised for Approval |
C |
24 Sep 2013 |
4, 5 |
4(i) – Updated table 2 5 – updated general notes of installation
measures |
D |
8 Oct 2013 |
2 (vi), 4 (ii), Appendix C |
2(vi) - Only generator will be use on the
vessel. 4(ii) – update 4(ii) clause App. C – add typical drawing for acoustic
decoupling measures |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Status
of Page Revision:
Rev. ð Section Ê |
A |
B |
C |
D |
E |
F |
G |
H |
I |
J |
K |
L |
M |
N |
O |
P |
Q |
R |
S |
T |
U |
1 |
X |
X |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
2 |
X |
X |
|
x |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
3 |
X |
X |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
4 |
X |
X |
X |
x |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
5 |
X |
X |
X |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Rev. ð SectionÊ |
A |
B |
C |
D |
E |
F |
G |
H |
I |
J |
K |
L |
M |
N |
O |
P |
Q |
R |
S |
T |
U |
Appendix A |
X |
X |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Appendix B |
X |
X |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Appendix C |
|
|
X |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Contract no. :
HY/2012/08
Project Title :
Tuen Mun – Chek Lap Kok
Link, Northern Connection Sub-Sea
Tunnel Section
Contract Period : From 31st July 2013 to 25th
October 2018
The Client :
Government of Hong Kong Special
Administration Region
–
Highways Department
The Supervising
Officer : AECOM
Asia Company Limited
The Main
Contractor : Dragages - Bouygues Joint Venture
Nature of Work : The design and/or construction for the section of TM-CLKL between Tuen Mun Area 40 and the HKBCF, include the following scope of work:
(i) Design and construction of sub-sea TBM tunnels (two tubes with cross passages) across the Urmston Road, connecting Tuen Mun Area 40 and HKBCF, of approximately 4 km in length with dual 2-lane carriageway (Figure 1);
(ii)
Design and construction of cut-and-cover tunnels
(two boxes with cross passages) at both the southern landfall (Figure 3) and the northern landfall (Figure 2) for construction of approach
roads to the sub-sea TBM tunnels, of approximately 1.5km in length;
(iii)
Construction of northern landfall (Figure 2) reclamation of approximately
16.5 hectares and about 2.0km long seawalls;
(iv)
Design and construction of ventilation buildings
at the southern and northern landfalls;
(v)
Design and construction of at-grade roads at the
southern and northern landfalls;
(vi)
Construction of extension of the existing 4-cell
box culvert adjacent to RTT;
(vii)
Provision of a temporary pontoon for the
affected existing Government berths at RTT;
(viii)
Design and construction for modification of a
section of vertical seawall of approximately 220m in length at the southern
landfall (Figure 3) to sloping
seawall;
(ix)
Design and construction of associated civil,
structural, building, geotechnical, marine, environmental protection, drainage
and sewerage, waterworks and utility works;
(x)
Design and construction of advance SEM
provisions to facilitate installation of E&M, TCSS and other utilities
including tunnel ventilation, tunnel lighting, tunnel fire services, mechanical
ventilation & air- conditioning, high voltage power supply, low voltage
power supply, fire services, plumbing & drainage, central monitoring &
control system and implementation of an EM&A programme for the works under
this Contract.
Figure 1 – HY/2012/08 Project
Figure 2 – Northern Landfall
Figure 3 – Southern
Landfall
(IV) TABLE OF CONTENTS
(I)
Document StatuS
(II)
PROJECT DETAILS
(III)
SITE LAYOUT PLAN
(IV)
Table Of Contents
2. MArine Construction Noise
Source
3. Proposed Acoustic Decoupling
Measures
4. Implementation of Acoustic
Decoupling Measures
5. General Notes on
Installation Measures
AppendiCES
Appendix
A Photos
of Noisy Equipment and proposed working vessels
Appendix B ISolation Material PRoduct Literature
Appendix C typical
set up of the acoustic decoupling measures for the generator
(i)
The
Tuen Mun – Chek Lap Kong Link serves to connect Tuen Mun with the Chek Lap Kok
and the Hong Kong - Zhuhai - Macau Bridge.
(ii)
Highways
Department has awarded this Contract to Dragages – Bouygues Joint Venture. Project
details are given in Section II above. The Contract scope is depicted in
Figures 1, 2 and 3.
(iii)
This
plan is prepared in accordance with Condition 2.5 of the Environmental Permit (EP-354/2009/A),
which requires the Permit Holder to submit to the Director of Environmental Protection
the design and implementation of acoustic decoupling measures applied during
bored piling, dredging and reclamation works.
2.
MArine Construction Noise
Source
(i)
Under
the design of the HY/2012/08 Contract, there will be no marine bored piling
works and may have limited sheet piling works. The primary marine works will be
dredging and reclamation to form the Northern Landfall (Figure 2). The Southern Landfall (Figure 3) will be reclaimed by others and the sub-sea tunnel (Figure 1) will be constructed by tunnel
boring machines (TBM), in rocks underneath the marine environment.
(ii)
The noise
sources from marine works at the Northern Landfall (Figure 2), during the construction phase, will mainly comprise of
the following activities:
a. Installation of silt curtain;
b. Installation of a temporary seawall, which may be a
steel structure, concrete block structure or rock fill. Sheet piling or similar
methods may be used;
c. Dredging at the base of load bearing
structures and other engineering elements, such as the seawall;
d. Laying geotextile
e. Installation of band drain;
f. Sand and reclamation filling.
(iii) According to Section 8.11.9.29 of the approved EIA Report (Agreement No. CE 52/2007 (HY)), the use of high-frequency sounds by Chinese White Dolphins make them less vulnerable to the effects of dredgers and large vessels, which generally produce very low frequency noises of less than a few kilohertz. These types of vessels are thus not considered to be a significant source of acoustic disturbance and will not be considered as sources of noise and vibration for the implementation of acoustic decoupling measures.
(iv) According to Section 8.14.4.13 of the approved EIA Report (Agreement No. CE 52/2007 (HY)), construction equipment can be noisy and, when such pieces of equipment are used on the water or in coastal waters, some of the sound may be transmitted into water and affect small cetaceans as noise pollution. Air compressors and other noisy equipment that must be mounted on steel piling barge should be acoustically de-coupled to the greatest extent feasible. Section 8.14.4.13 of the EIA Report suggests the use of rubber tires or air-filled tires to de-couple noise (i.e. wheel mounted air compressors or generators are de-couples from the deck).
(v)
It is
envisaged that there will be 6 types of working vessels working in the Northern
Landfall dredging and reclamation area. Some of them are support vessels and
will not carry separate noisy equipment. Not all of the noisy equipment will be
operated at any one time.
(vi)
The noisy
equipment allocated on the working vessels is listed in Table 1. Only generator will be mounted on the vessels, together
with acoustic decoupling measures. No other noisy equipment will be use on
board. The photos of the noisy equipment are shown in Appendix A. The list will be updated regularly and communicated to
the SOR, ETL and IEC/ENPO.
Table 1: Vessel and Noisy Equipment Inventory
Working Vessels |
Noisy Equipment on Working Vessels |
Expected No of generators |
2400T
Derrick Barge x 8 |
Generator, Silenced, 75dB (A)
at 7m (Diesel, 35.81kW, 1.5 Tons. Approx.) only installed in 2 nos. of barge |
2 |
850hp
Tug Boat x 4 |
None |
0 |
1000m3
Split Hopper Barge x 7 |
Generator, Silenced, 75dB
(A) at 7m (Diesel, 35.81kW, 1.5 Tons. Approx.) only installed in 5 nos.
of barge |
5 |
Flat
Top Barge x 1 |
Generator, Silenced, 75dB
(A) at 7m (Diesel, 35.81kW, 1.5 Tons. Approx.) x 1/barge |
1 |
Grab
Dredger x 2 |
Generator, Silenced, 75dB (A)
at 7m (Diesel, 35.81kW, 1.5 Tons. Approx.) x 2/dredger |
4 |
Motor Sampan |
No Noisy Equipment, for
transportation only |
0 |
3.
Proposed Acoustic Decoupling Measures
(i) The same noise isolation pad previously approved in other Hong Kong – Zhuhai – Macau Bridge (HZMB) projects (e.g. Link Road Contracts HY/2011/03, HY/2011/09 and HY/2012/07) is proposed to be used for this Contract. This product was originally developed and marketed as noise dampening underlays for building construction. Product literature of the isolation material is given in Appendix B.
(ii) If sheet piling is to be carried out, isolation pads shall be fitted between the vibrator clamp and the sheet pile, such that the path from noisy equipment through the sheet pile to the marine environment is broken.
(iii) The typical set up of the acoustic decoupling measures for the generator and the sheet pile vibrator are shown in Appendix C.
4.
Implementation of Acoustic Decoupling Measures
(i)
The
dimensions of the proposed isolation pad for the noisy equipment are
given in Table 2.
Table 2: Vessel and Noisy Equipment Inventory: Footprint Area of Isolation Padding
Proposed Working Vessel |
Noisy Equipment
Identified on Working Vessel |
Envisaged Dimension of
Proposed Isolation Pad (LxWxH) Each |
2,400T Derrick Barge x 8 |
Generator (Diesel) |
2m x 1m x 30mm approx. |
850hp Tug Boat x 4 |
None |
N.A. |
1,000m3 Split
Hopper Barge x 7 |
Generator (Diesel) |
2m x 1m x 30mm approx. |
Flat Top Barge x 1 |
Generator (Diesel) |
2m x 1m x 30mm approx. |
Grab Dredger x 2 |
Generator (Diesel) |
2m x 1m x 30mm each
(approx.) |
Motor Sampan |
None |
N.A. |
(ii)
Only
generator will be mounted on the vessels, together with acoustic decoupling
measures. No other noisy equipment will be use on board.
(iii)
Noisy
equipment will be fixed on noise decoupling pads instead of being mounted
directly on the deck. The Contractor will ensure the foundation of the
equipment is flat and level prior to installation. Adequate clearance all
around the noisy equipment will be kept to avoid vibration transmitted to other
materials and machinery.
(iv)
Those
noisy equipments, such as engines, which are welded directly onto the deck of
vessel, should provide other mitigating measures such as alternative work
schedule to minimize the vibration transmission to the sea.
5.
General Notes on Installation Measures
(i)
To
forbid direct vibration transmission, adequate plinth clearance shall be kept
all around.
(ii)
Close
all panels or doors of generators when in use.
(iii)
To
avoid noise breakout and the undesirable sound paths through gaps, the foundation
where the equipment to be placed shall be flat and level.
(iv)
To
further eliminated the sound generation from noisy parts, flexible bellows
silencers, mufflers shall be applied when necessary.
END OF CONTENT
Appendix
A - Photos of Noisy Equipment and Proposed working
vessels
Noisy
Equipment
|
Generator
on vessel board |
working vessels
|
|
2400T Derrick Barge |
850hp Tug Boat |
|
|
1000m3 Split Hopper Barge |
Flat Top Barge |
|
|
Grab Dredger |
Motor Sampan |
Appendix
B - ISOLATION MATERIAL PRODUCT LITERATURE
Appendix C - typical set up of the acoustic decoupling measures for the generator